Bangalore/Project record

K-RERA · the public record

ROYAL NEST

Anekal · WONE 8 ESTATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

35%construction reportedQ1 2026 filing
95units not bookedof 104 · Q1 2026 filing
30 Jun 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

1 BHK
5
2 BHK
75
3 BHK
24

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.3registered acres

77.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/180825/008007

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2028
Land area5,463 sq m (1.3 acres)
Homes registered104
Tower/wing entries2
Unit mix5 × 1 BHK, 75 × 2 BHK, 24 × 3 BHK

In context

Density77 homes per acre
Density in context52nd percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units104Total inventory registered with K-RERA.
Official carpet area7,880 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area15,862 sqmUseful scale context when comparing density and project cost.
Registered land area5,463 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.22Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)104Separate filed counts; these categories may overlap and are not added together.
Covered-parking field102Separate filed counts; these categories may overlap and are not added together.
Open-parking field10Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberSTRRPA/TP/CC/220/2024-25/25-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date10-06-2025
Project start date01-07-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1 BHK55%104 sqm
2 BHK7572%5,494 sqm
3 BHK2423%2,175 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BLOCK-A4252514.95 m
BLOCK-B4797914.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 104 official flat/unit rows, matching the 104 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK7563.5-82.7 sqm33.5-41.0 sqm75
3 BHK2476.0-107.4 sqm42.1-57.0 sqm24
1 BHK520.8 sqm14.8-17.8 sqm5

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BLOCK-B7963.5-107.4 sqm33.5-57.0 sqm79
BLOCK-A2520.8-99.7 sqm14.8-50.5 sqm25
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-101BLOCK-A03 BHK90.3 sqm42.1 sqm1
A-102BLOCK-A01 BHK20.8 sqm14.8 sqm1
A-103BLOCK-A02 BHK67.2 sqm35.4 sqm1
A-104BLOCK-A02 BHK67.2 sqm35.4 sqm1
A-105BLOCK-A02 BHK64.8 sqm39.7 sqm1
A-201BLOCK-A13 BHK99.7 sqm50.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 27 compliance document slots are filed as under process / not yet usable: Organization Structure.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSHUBHAM DALMIA3107692018Bengaluru Urban, Karnataka - 560027
EngineerRamesh Muthu DBCCL/BL-3.6/SE-0031/21-222021Bengaluru Urban, Karnataka - 560078
ArchitectSANJAY DHAVALICA/2003/315112003Bengaluru Urban, Karnataka - 560078
ContractorWONE 8 ESTATES PRIVATE LIMITED-2023Bengaluru Urban, Karnataka - 560068

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.81 Cr collected from buyers, ₹0.36 Cr withdrawn from the project's escrow account.

Construction progress20% → 35% (+15 pts)
Units sold/booked as registered9/104 (9%)
Buyer collections in available QPRs₹1.23 Cr
Escrow withdrawals in available QPRs₹0.57 Cr (0.46x collections)
  • Construction progress moved from 20% to 35% across the filed QPR window.
  • The builder has drawn 0.46x of buyer collections from escrow (about 46% of the ₹1 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹38.4 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC BTM Layout IFSC Code : HDFC0000885 Pin Code : 560068. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub13 km
Bellandur–Marathahalli belt15 km
Electronic City17 km
MG Road / city centre25 km
Outer Ring Road / Manyata28 km
Kempegowda Int'l Airport38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Wone Estates.

Other RERA-registered projects in Sarjapura

Major developers building in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Royal Nest?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026