Bangalore/Project record

K-RERA · the public record

S.V.SIGNATURE

Bengaluru East · S.V.DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2021declared completionK-RERA registration · read 20 Sep 2026
258registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.3registered acres

113.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/181010/002057

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2021
Land area9,207 sq m (2.3 acres)
Homes registered258
Tower/wing entries3

In context

Density113.4 homes per acre
Density in context92nd percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units258Total inventory registered with K-RERA.
Registered land area9,207 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~2.99Sanctioned floor-area ratio (≈27,533 sqm sanctioned FAR area ÷ 9,207 sqm land) — higher means a denser vertical build.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)284Separate filed counts; these categories may overlap and are not added together.
Open-parking field12Separate filed counts; these categories may overlap and are not added together.
Garage field294Separate filed counts; these categories may overlap and are not added together.
Project start date01-07-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A910852-
Tower B94092-
Tower C9110140-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 258 official flat/unit rows, matching the 258 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK19772.1-78.2 sqm32.6-37.1 sqm197
3BHK2891.7-96.8 sqm40.9-44.9 sqm28
2.5BHK2080.1-83.2 sqm38.5-38.6 sqm20
1BHK1346.4-50.1 sqm21.8-23.7 sqm13

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower C11046.4-93.0 sqm21.8-43.6 sqm110
Tower A10850.1-96.8 sqm23.4-44.9 sqm108
Tower B4072.3-83.2 sqm32.6-38.6 sqm40
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001Tower A02BHK74.3 sqm33.5 sqm1
A-002Tower A01BHK50.1 sqm23.4 sqm1
A-003Tower A02BHK75.6 sqm34.0 sqm1
A-004Tower A02BHK74.5 sqm33.5 sqm1
A-005Tower A02BHK74.4 sqm33.5 sqm1
A-008Tower A02BHK72.7 sqm33.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

3 of 20 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2021, extended (Covid Extension) to 30 Mar 2022 — both dates have passed with no OC on file. An extension application filed on 15 Jul 2022 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectSreenivasa Rao G-200317th main, 24th cross Banashankari 2nd Stage
Structural engineerGirish M---

Builder track record

RERA filing

Developers has 62 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Developers”) (average reported construction progress 81%). 19 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹30.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd. Nehrunagar (IFSC KARB0000063, a/c …9501). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub4 km
Bellandur–Marathahalli belt7 km
Outer Ring Road / Manyata12 km
MG Road / city centre12 km
Electronic City18 km
Kempegowda Int'l Airport23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Developers.
Developers has 54 projects registered in Bangalore, 10 completed.
2 complaints on the K-RERA register against Developers in Bangalore.

Other projects by this builder in Bangalore

36 Park Avenue Phase III
Filing overdue · 100% built
36 Park Avenue Phase-II
Filing overdue · 100% built
Amantran Anant Shubh Vihaar
Filing overdue · 65% built · 7% sold
G9 Vinyas 2
Filing overdue · 100% built
Jyotichandra
Filing overdue · 93% built · 17% sold
Kamadhenu Heights
Filing overdue · 46% built · 5% sold

Other RERA-registered projects in Mahadevapura

Major developers building in Mahadevapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in S.v.signature?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026