RERA Property Intelligence Report · Preview

S.V.SIGNATURE

S.V.DEVELOPERS · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/181010/002057

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
60
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

258
Registered units
₹79.0 Cr
Est. construction cost
Units profiled
26
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units258Total inventory registered with K-RERA.
Registered land area9,207 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~2.99Sanctioned floor-area ratio (≈27,533 sqm sanctioned FAR area ÷ 9,207 sqm land) — higher means a denser vertical build.
Registered towers/wings3Official tower/wing count in the K-RERA detail page.
Parking disclosed284 total (12 open) — 1.10 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-07-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower A910852-
Tower B94092-
Tower C9110140-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 258 official flat/unit rows, matching the 258 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK19772.1-78.2 sqm32.6-37.1 sqm197
3BHK2891.7-96.8 sqm40.9-44.9 sqm28
2.5BHK2080.1-83.2 sqm38.5-38.6 sqm20
1BHK1346.4-50.1 sqm21.8-23.7 sqm13

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower C11046.4-93.0 sqm21.8-43.6 sqm110
Tower A10850.1-96.8 sqm23.4-44.9 sqm108
Tower B4072.3-83.2 sqm32.6-38.6 sqm40
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001Tower A02BHK74.3 sqm33.5 sqm1
A-002Tower A01BHK50.1 sqm23.4 sqm1
A-003Tower A02BHK75.6 sqm34.0 sqm1
A-004Tower A02BHK74.5 sqm33.5 sqm1
A-005Tower A02BHK74.4 sqm33.5 sqm1
A-008Tower A02BHK72.7 sqm33.0 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~825 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a mid-scale project — 258 homes across 3 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 284 parking spaces for 258 homes (~1.1 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~36 sqm per home; across all 258 homes that is ~100% of the plot — a healthy sign: buyers collectively hold close to all the land. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

3 of 20 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2021, extended (Covid Extension) to 30 Mar 2022 — both dates have passed with no OC on file. An extension application filed on 15 Jul 2022 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectSreenivasa Rao G-200317th main, 24th cross Banashankari 2nd Stage
Structural engineerGirish M---

Builder track record

RERA filing

Developers has 60 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Developers”) (average reported construction progress 75%). 16 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹30.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd. Nehrunagar (IFSC KARB0000063, a/c …9501). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub4 km
Bellandur–Marathahalli belt7 km
Outer Ring Road / Manyata12 km
MG Road / city centre12 km
Electronic City18 km
Kempegowda Int'l Airport23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Developers.
Developers has 56 projects registered in Bangalore, 9 completed.
2 complaints on the K-RERA register against Developers in Bangalore.

Other projects by this builder in Bangalore

36 Park Avenue Phase III
Filing overdue · 100% built
36 Park Avenue Phase-II
Filing overdue · 100% built
A R Pearl Apartment
Filing overdue · 95% built · 68% sold
Avani Abode
Filing overdue · 98% built
Amantran Anant Shubh Vihaar
Filing overdue · 65% built · 7% sold
G9 Vinyas 2
Filing overdue · 100% built

Other RERA-registered projects in Mahadevapura

Major developers building in Mahadevapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.