SHIGRA PALMS
· SRISHIGRA BUILDERS DEVELOPERS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 16 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
Not recorded
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 16 Jul 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 16 Jul 2026
The whole registration
4.0registered acres
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1265/339/PR/171214/001624
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered land area | 16,359 sqm | The land area attached to this K-RERA registration. |
| Open-parking field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 28-07-2017 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
All 15 standard compliance document slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 31 Aug 2020, extended (Covid Extension) to 31 May 2021 — both dates have passed with no OC on file.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Venkat Subramaniam K vs SHIGRA PLAMS | NOC to be issued, Compensation for 6 years delay, Project Amenities to be completed as per project brochure | AUTHORITY | 17/05/2025 |
| LAXMAN BANDI vs M/S SRISHIGRA BUILDERS DEVELOPERS | WE NEED REFUND OF OUR HARD EARNED MONEY THROUGH OUT OF LIFE | AUTHORITY | 12/01/2023 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (1 complaint listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/210917/0008346 17-09-2021 | The Builders RAMESH REDDY , BHASKAR REDDY, MANJUNAATH have cheated us by looting our life long hard earned money | SHIGRA PALMS | DISPOSED AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
RERA 70% project account is on file: ICICI Bank H S R Layout 7 Sector (IFSC ICIC0003168, a/c …0093). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Bellandur–Marathahalli belt | 6 km |
| MG Road / city centre | 7 km |
| Electronic City | 8 km |
| Whitefield IT hub | 14 km |
| Outer Ring Road / Manyata | 14 km |
| Kempegowda Int'l Airport | 32 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.