19 Jul 2020declared completionK-RERA registration · read 20 Sep 2026
20registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

19 Jul 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.3registered acres

63.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/190711/002660

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion19 July 2020
Land area1,271 sq m (0.3 acres)
Homes registered20
Tower/wing entries2

In context

Density63.7 homes per acre
Density in context31st percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units20Total inventory registered with K-RERA.
Registered land area1,271 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)21Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date20-07-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
resident block41618-
hostel block443-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 20 official flat/unit rows, matching the 20 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK12102.4-116.5 sqm649.7-748.4 sqm12
2BHK466.3 sqm508.2 sqm4
4BHK3173.8 sqm1,047.0 sqm3
SHOP1173.8 sqm1,047.0 sqm0 (1 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
resident block1666.3-116.5 sqm508.2-748.4 sqm16
hostel block4173.8 sqm1,047.0 sqm3 (1 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1resident block13BHK102.4 sqm649.7 sqm1
2resident block13BHK108.1 sqm699.0 sqm1
3resident block12BHK66.3 sqm508.2 sqm1
4resident block13BHK116.5 sqm748.4 sqm1
101resident block23BHK102.4 sqm649.7 sqm1
102resident block23BHK108.1 sqm699.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

4 of 16 compliance document slots are filed as Not Applicable; the remaining 12 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 19 Jul 2020, extended (Covid Extension) to 19 Apr 2021 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Penalty orders on record:

ViolationUnder sectionPenaltyOrder date
Non Submission Of Annual Report 2021 22Section 4(2)(l)(D)₹239,63514/12/2023

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/210215/0007638
15-02-2021
Delay in possession, agreement breach, sale area disputeSNR Verity (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/210301/0007711
01-03-2021
Amenities pending & RERA registration expiredSNR Verity (another project by this promoter)DISPOSED AUTHORITY BENCH5
CMP/221107/0010209
07-11-2022
Celing (roof) and walls waterproofing is not completed for Flat A302 SNR VeritySNR Verity (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Builder track record

RERA filing

Snr Square has 4 other K-RERA-registered projects in our records. 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹24.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Industrial Development Bank of India HSR Layout (IFSC IBKL0000896, a/c …1893). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bellandur–Marathahalli belt5 km
Electronic City6 km
MG Road / city centre10 km
Whitefield IT hub13 km
Outer Ring Road / Manyata16 km
Kempegowda Int'l Airport34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Snr Square. View Snr Square's full track record →
Snr Square has 5 projects registered in Bangalore.
9 complaints on the K-RERA register against Snr Square in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in HSR Layout

Major developers building in HSR Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in SNR Mayfair?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026