The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Oct 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 6 filed quarterly reports, Dlf Gardencity Enclave records ₹45.39 Cr paid into and ₹-13.59 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹66.31 Cr.
₹45.39 Cr
into the escrow account
₹-13.59 Cr
withdrawn
₹66.31 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q4 | 0 | 367 |
| 2025 Q1 | 0 | 367 |
| 2025 Q2 | 8 | 367 |
| 2025 Q3 | 2 | 367 |
| 2025 Q4 | 0 | 367 |
| 2026 Q1 | 1 | 367 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q4 | ₹19.29 Cr | ₹-68 L | ₹53.13 Cr |
| 2025 Q1 | ₹5.49 Cr | ₹-1.86 Cr | ₹56.75 Cr |
| 2025 Q2 | ₹4.40 Cr | ₹-1.00 Cr | ₹60.16 Cr |
| 2025 Q3 | ₹4.14 Cr | ₹-3.00 Cr | ₹61.29 Cr |
| 2025 Q4 | ₹4.02 Cr | ₹-3.50 Cr | ₹61.81 Cr |
| 2026 Q1 | ₹8.05 Cr | ₹-3.55 Cr | ₹66.31 Cr |
Builder Record
DLF has 43 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 32 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Alameda Central — declared 2027-09-08 · OC on record
- Arcade 68 — declared 2027-11-10 · OC on record
- Central 67 — declared 2027-12-31 · OC on record
- Central 74 — declared 2028-09-06
Location & Connectivity
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 7 km |
| Golf Course Road belt | 17 km |
| Cyber City / DLF Cyber Hub | 18 km |
| Udyog Vihar | 18 km |
| IGI Airport, Delhi | 23 km |
| Connaught Place, Delhi | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.