HRERA · the public record
Gateway95
GATEWAY95 SECTOR95 VILLAGE DH ORKA TEHSIL HARSARU DISTRICT GURUGRAM HARYANA · Solutrean Building Technologies
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Aug 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 6 filed quarterly reports, Gateway95 records ₹28.38 Cr paid into and ₹28.39 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹2 L.
₹28.38 Cr
into the escrow account
₹28.39 Cr
withdrawn
₹2 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q1 | 2 | 124 |
| 2024 Q2 | 5 | 124 |
| 2024 Q3 | 7 | 124 |
| 2024 Q4 | 12 | 124 |
| 2025 Q1 | 6 | 124 |
| 2025 Q2 | 0 | 124 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q1 | ₹9.84 Cr | ₹9.86 Cr | ₹1 L |
| 2024 Q2 | ₹4.33 Cr | ₹4.33 Cr | ₹1 L |
| 2024 Q3 | ₹2.75 Cr | ₹2.73 Cr | ₹2 L |
| 2024 Q4 | ₹5.26 Cr | ₹4.50 Cr | ₹76 L |
| 2025 Q1 | ₹5.20 Cr | ₹5.01 Cr | ₹97 L |
| 2025 Q2 | ₹1.00 Cr | ₹1.96 Cr | ₹2 L |
Builder Record
Solutrean Building Technologies has 1 other Gurgaon project on the HRERA register; 0 are past the declared completion date with no OC yet. Read it as a spot-check list for a pattern, not a delay rate.
- Gateway Plaza 95 — declared 2027-09-09
Location & Connectivity
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 7 km |
| Golf Course Road belt | 20 km |
| Cyber City / DLF Cyber Hub | 21 km |
| Udyog Vihar | 21 km |
| IGI Airport, Delhi | 26 km |
| Connaught Place, Delhi | 40 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.