Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
31 Dec 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 18 filed quarterly reports, Godrej Meridien-ii records ₹163.07 Cr paid into and ₹164.07 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.
₹163.07 Cr
into the escrow account
₹164.07 Cr
withdrawn
₹0 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2022 Q1 | 12 | 344 |
| 2022 Q2 | 16 | 344 |
| 2022 Q3 | 23 | 344 |
| 2022 Q4 | 15 | 344 |
| 2023 Q1 | 13 | 344 |
| 2023 Q2 | 1 | 344 |
| 2023 Q3 | 3 | 344 |
| 2023 Q4 | 0 | 344 |
| 2024 Q1 | 0 | 134 |
| 2024 Q2 | 0 | 134 |
| 2024 Q3 | 0 | 134 |
| 2024 Q4 | 0 | 134 |
| 2025 Q1 | 1 | 134 |
| 2025 Q2 | 0 | 134 |
| 2025 Q3 | 0 | 134 |
| 2025 Q4 | 0 | 134 |
| 2026 Q1 | 0 | 134 |
| 2026 Q2 | 0 | 911 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2022 Q1 | ₹7.47 Cr | ₹7.17 Cr | ₹39 L |
| 2022 Q2 | ₹14.19 Cr | ₹14.39 Cr | ₹19 L |
| 2022 Q3 | ₹14.08 Cr | ₹14.10 Cr | ₹17 L |
| 2022 Q4 | ₹7.97 Cr | ₹8.06 Cr | ₹8 L |
| 2023 Q1 | ₹9.48 Cr | ₹9.16 Cr | ₹40 L |
| 2023 Q2 | ₹3.04 Cr | ₹3.42 Cr | ₹30.17 Cr |
| 2023 Q3 | ₹1.47 Cr | ₹1.49 Cr | ₹0 L |
| 2023 Q4 | ₹8.23 Cr | ₹6.92 Cr | ₹1.31 Cr |
| 2024 Q1 | ₹22.48 Cr | ₹20.56 Cr | ₹3.22 Cr |
| 2024 Q2 | ₹6.24 Cr | ₹9.30 Cr | ₹16 L |
| 2024 Q3 | ₹15.05 Cr | ₹14.93 Cr | ₹12 L |
| 2024 Q4 | ₹2.73 Cr | ₹3.93 Cr | ₹0 L |
| 2025 Q1 | ₹13.41 Cr | ₹13.41 Cr | ₹0 L |
| 2025 Q2 | ₹1.15 Cr | ₹1.15 Cr | ₹0 L |
| 2025 Q3 | ₹66 L | ₹66 L | ₹0 L |
| 2025 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2026 Q1 | ₹17.71 Cr | ₹17.71 Cr | ₹0 L |
| 2026 Q2 | ₹17.71 Cr | ₹17.71 Cr | ₹0 L |
Builder Record
Godrej Properties has 18 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 3 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Godrej Air Phase-i — declared 2027-06-29
- Godrej Air Phase-ii — declared 2027-09-30
- Godrej Air Phase-iii — declared 2027-03-29
- Godrej Air Phase-iv — declared 2027-06-29
Location & Connectivity
The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Udyog Vihar | 9 km |
| Cyber City / DLF Cyber Hub | 10 km |
| IGI Airport, Delhi | 12 km |
| Golf Course Road belt | 13 km |
| IMT Manesar | 17 km |
| Connaught Place, Delhi | 26 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.