Gurgaon/Project record

HRERA · the public record

Grand Central 114

SECTOR 114, GURUGRAM · Candeo Projects

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

210units in latest filingQ4 2023 filing
8units sold that quarterQ4 2023 filing
18 Jan 2027registration expiryHRERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

registration expiry

18 Jan 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

HRERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 6 filed quarterly reports, Grand Central 114 records ₹75.16 Cr paid into and ₹76.06 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹4.69 Cr.

₹75.16 Cr

into the escrow account

₹76.06 Cr

withdrawn

₹4.69 Cr

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2022 Q313210
2022 Q412210
2023 Q110210
2023 Q215210
2023 Q38210
2023 Q48210

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2022 Q3₹7.73 Cr₹6.28 Cr₹7.05 Cr
2022 Q4₹5.29 Cr₹11.49 Cr₹85 L
2023 Q1₹7.44 Cr₹8.11 Cr₹19 L
2023 Q2₹17.95 Cr₹16.97 Cr₹1.17 Cr
2023 Q3₹9.90 Cr₹9.23 Cr₹1.84 Cr
2023 Q4₹26.84 Cr₹23.99 Cr₹4.69 Cr

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Udyog Vihar8 km
Cyber City / DLF Cyber Hub9 km
IGI Airport, Delhi9 km
Golf Course Road belt13 km
IMT Manesar21 km
Connaught Place, Delhi23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Candeo Projects.

Other RERA-registered projects in Bajghera

Major developers building in Bajghera

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.