Kavyam-phase-1
SECTOR-108, DHARAMPUR, GURUGR AM · Agrante Realty
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Nov 2022
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 18 filed quarterly reports, Kavyam-phase-1 records ₹68.78 Cr paid into and ₹65.71 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.
₹68.78 Cr
into the escrow account
₹65.71 Cr
withdrawn
₹0 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Official Unit Inventory
723 apartments filed across 1 carpet-area configurations, 1 tower, carpet areas from 484 to 484 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).
| Carpet area | (metric) | Units of this size |
|---|---|---|
| 484 sq ft | 45.0 sq m | 723 |
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2021 Q1 | 0 | — |
| 2021 Q2 | 0 | — |
| 2021 Q3 | 0 | — |
| 2021 Q4 | 0 | — |
| 2022 Q1 | 0 | — |
| 2022 Q2 | 0 | — |
| 2022 Q3 | 0 | — |
| 2022 Q4 | 0 | — |
| 2023 Q1 | 0 | — |
| 2023 Q2 | 0 | — |
| 2023 Q3 | 0 | — |
| 2023 Q4 | 0 | — |
| 2024 Q1 | 1 | 723 |
| 2024 Q2 | 7 | 723 |
| 2024 Q3 | 3 | 723 |
| 2024 Q4 | 0 | 723 |
| 2025 Q1 | 0 | 723 |
| 2025 Q2 | 0 | — |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2021 Q1 | ₹5.55 Cr | ₹0 L | ₹2 L |
| 2021 Q2 | ₹12.10 Cr | ₹11.99 Cr | ₹13 L |
| 2021 Q3 | ₹6.95 Cr | ₹7.06 Cr | ₹2 L |
| 2021 Q4 | ₹14.27 Cr | ₹17.07 Cr | ₹28 L |
| 2022 Q1 | ₹1.97 Cr | ₹2.24 Cr | ₹0 L |
| 2022 Q2 | ₹9.99 Cr | ₹9.99 Cr | ₹1 L |
| 2022 Q3 | ₹4.45 Cr | ₹4.45 Cr | ₹1 L |
| 2022 Q4 | ₹2.53 Cr | ₹2.53 Cr | ₹0 L |
| 2023 Q1 | ₹2.18 Cr | ₹2.17 Cr | ₹1 L |
| 2023 Q2 | ₹1.71 Cr | ₹1.63 Cr | ₹0 L |
| 2023 Q3 | ₹92 L | ₹67 L | ₹0 L |
| 2023 Q4 | ₹92 L | ₹67 L | ₹0 L |
| 2024 Q1 | ₹96 L | ₹95 L | ₹1 L |
| 2024 Q2 | ₹1.43 Cr | ₹78 L | ₹66 L |
| 2024 Q3 | ₹2.43 Cr | ₹3.10 Cr | ₹0 L |
| 2024 Q4 | ₹41 L | ₹41 L | ₹0 L |
| 2025 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2025 Q2 | ₹0 L | ₹0 L | ₹0 L |
Location & Connectivity
The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Udyog Vihar | 10 km |
| Cyber City / DLF Cyber Hub | 10 km |
| IGI Airport, Delhi | 12 km |
| Golf Course Road belt | 14 km |
| IMT Manesar | 18 km |
| Connaught Place, Delhi | 26 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.