HRERA · the public record
Rmg Residency
SECTOR-37C, GURUGRAM · Rmg Developers
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
31 Dec 2019
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 12 filed quarterly reports, Rmg Residency records ₹20.32 Cr paid into and ₹19.82 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹93 L.
₹20.32 Cr
into the escrow account
₹19.82 Cr
withdrawn
₹93 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q1 | 7 | 724 |
| 2023 Q2 | 4 | 724 |
| 2023 Q3 | 4 | 724 |
| 2023 Q4 | 0 | 724 |
| 2024 Q1 | 0 | 724 |
| 2024 Q2 | 3 | 724 |
| 2024 Q3 | 2 | 724 |
| 2024 Q4 | 0 | 724 |
| 2025 Q1 | 0 | 724 |
| 2025 Q2 | 1 | 724 |
| 2025 Q3 | 5 | 724 |
| 2025 Q4 | 0 | 724 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q1 | ₹2.19 Cr | ₹1.74 Cr | ₹89 L |
| 2023 Q2 | ₹2.09 Cr | ₹1.76 Cr | ₹1.22 Cr |
| 2023 Q3 | ₹6.92 Cr | ₹5.94 Cr | ₹2.21 Cr |
| 2023 Q4 | ₹95 L | ₹1.79 Cr | ₹1.37 Cr |
| 2024 Q1 | ₹1.38 Cr | ₹1.69 Cr | ₹1.05 Cr |
| 2024 Q2 | ₹1.91 Cr | ₹1.61 Cr | ₹1.35 Cr |
| 2024 Q3 | ₹1.25 Cr | ₹2.52 Cr | ₹9 L |
| 2024 Q4 | ₹74 L | ₹69 L | ₹14 L |
| 2025 Q1 | ₹55 L | ₹63 L | ₹6 L |
| 2025 Q2 | ₹1.47 Cr | ₹1.08 Cr | ₹45 L |
| 2025 Q3 | ₹75 L | ₹18 L | ₹1.02 Cr |
| 2025 Q4 | ₹12 L | ₹21 L | ₹93 L |
Location & Connectivity
The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Cyber City / DLF Cyber Hub | 11 km |
| Udyog Vihar | 11 km |
| Golf Course Road belt | 11 km |
| IMT Manesar | 12 km |
| IGI Airport, Delhi | 16 km |
| Connaught Place, Delhi | 30 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.