HRERA · the public record
Westerlies
SECTOR 108 · Experion Developers
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Jan 2024
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 6 filed quarterly reports, Westerlies records ₹4.24 Cr paid into and ₹4.20 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹4 L.
₹4.24 Cr
into the escrow account
₹4.20 Cr
withdrawn
₹4 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2022 Q4 | 0 | 23 |
| 2023 Q1 | 0 | 23 |
| 2023 Q2 | 0 | 23 |
| 2023 Q3 | 0 | 23 |
| 2023 Q4 | 10 | 23 |
| 2024 Q1 | 1 | 23 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2022 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2023 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2023 Q2 | ₹0 L | ₹0 L | ₹0 L |
| 2023 Q3 | ₹0 L | ₹0 L | ₹0 L |
| 2023 Q4 | ₹4.24 Cr | ₹0 L | ₹4.24 Cr |
| 2024 Q1 | ₹0 L | ₹4.20 Cr | ₹4 L |
Builder Record
Experion has 16 other Gurgaon projects on the HRERA register; 3 are past the declared completion date with no OC yet, 10 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Commercial Colony — declared 2018-10-22 · OC on record
- Heartsong Phase 6 — declared 2020-05-13 · OC on record
- Hub 108 — declared 2024-05-05
- One42 Golf Course Road — declared 2034-12-31
Location & Connectivity
The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Udyog Vihar | 10 km |
| Cyber City / DLF Cyber Hub | 10 km |
| IGI Airport, Delhi | 12 km |
| Golf Course Road belt | 14 km |
| IMT Manesar | 18 km |
| Connaught Place, Delhi | 26 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.