Gurgaon/Project record

HRERA · the public record

Westerlies

SECTOR 108 · Experion Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

172units in latest filingQ1 2024 filing
8units sold that quarterQ1 2024 filing
11 Sep 2024registration expiryHRERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

registration expiry

11 Sep 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

HRERA registration · read 20 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 6 filed quarterly reports, Westerlies records ₹55.61 Cr paid into and ₹58.26 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹4.10 Cr.

₹55.61 Cr

into the escrow account

₹58.26 Cr

withdrawn

₹4.10 Cr

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2022 Q413172
2023 Q15172
2023 Q24172
2023 Q39172
2023 Q414172
2024 Q18172

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2022 Q4₹11.10 Cr₹11.10 Cr₹3.11 Cr
2023 Q1₹7.17 Cr₹11 L₹25 L
2023 Q2₹11.09 Cr₹24.40 Cr₹50 L
2023 Q3₹8.35 Cr₹8.55 Cr₹30 L
2023 Q4₹7.37 Cr₹6.00 Cr₹1.67 Cr
2024 Q1₹10.53 Cr₹8.10 Cr₹4.10 Cr

Builder Record

Experion has 16 other Gurgaon projects on the HRERA register; 3 are past the declared completion date with no OC yet, 10 delivered. Read it as a spot-check list for a pattern, not a delay rate.

  • Commercial Colony — declared 2018-10-22 · OC on record
  • Heartsong Phase 6 — declared 2020-05-13 · OC on record
  • Hub 108 — declared 2024-05-05
  • One42 Golf Course Road — declared 2034-12-31

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Udyog Vihar10 km
Cyber City / DLF Cyber Hub10 km
IGI Airport, Delhi12 km
Golf Course Road belt14 km
IMT Manesar18 km
Connaught Place, Delhi26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Experion. View Experion's full track record →
Experion has 16 projects registered in Gurgaon, 11 completed, 2 past RERA deadline.

Other projects by this builder in Gurgaon

HUB 108
Past deadline · 100% sold
Windchants Phase -4,nursery School Site
Past deadline
Commercial Colony
Completed · 69% sold
Residential Plotted Colony
Completed

Other RERA-registered projects in Sector 37D

Major developers building in Sector 37D

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.

Own a unit in Westerlies?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026