Anna Nagar LBT CHS Ltd

Mumbai Suburban · Accanoor Associates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900007718

Delivery and registration

When is the project declared for completion?

Anna Nagar LBT CHS Ltd is registered with MahaRERA as P51900007718 and the promoter has declared completion for 31 Mar 2018.

31 Mar 2018

declared completion

102months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900007718
Registered on17 Aug 2017
Promoter-declared completion31 Mar 2018
Current statusCertificate Signed
Against todayabout 102 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Anna Nagar LBT CHS Ltd record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Accanoor Associates is the promoter of record on 2 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Anna Nagar LBT CHS Ltd in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Anna Nagar LBT CHS Ltd1G+8-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Anna Nagar LBT CHS Ltd, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007885015/04/2019Prashanth Shetty vs Deepak Raoorder passed
CC00600000039554107/05/2023PARADISE RESIDENCY CHSL (society) vs Deepak Rao, Proprietor M/s. Accanoor Associatesorder passed

A co-operative housing society is recorded as the complainant (PARADISE RESIDENCY CHSL), and MahaRERA has passed an order.

Location, Land & Connectivity

Located at Mumbai, Mumbai Suburban, 400016. Per the filed land record, the plot is bounded to the north by D P Road, to the south by C S No 97 pt, to the east by C S No 97 pt and to the west by C S No 97 pt. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Lower Parel / Worli business district5 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park11 km
Nariman Point / Fort13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Accanoor Associates is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Accanoor Associates

Accanoor Associates
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Mahim

Makhdoom Heights
possession by Nov 2026 · Naqi Developers Private Limited
Karpur Heights
possession by Dec 2026 · Parvasha Grihnirman Sanstha
ANJ Ananda
possession by Dec 2026 · A N J Recon LLP
Kapil Tirth
possession by Dec 2026 · Prathamesh Projects LLP
Moin Heights
possession by Dec 2026 · Mansoor Mehmood Sayyed
Royal Heights
possession by Dec 2026 · S.a. Enterprises

Major developers building in Mahim

Other RERA-registered projects in Mumbai City

Annapurna Sadan
possession by Jun 2028 · D R Developers
ANU-Smera Skylight
declared completion Dec 2025 · Balan Realty LLP
Anvaya
declared completion Nov 2024 · Kumar Matunga Project LLP
Anzar Elegance
possession by Dec 2028 · Mithila Developers
Aplite Sapphire
possession by Dec 2028 · Aplite Developers LLP
Aqdas Residency
possession by Dec 2027 · M/s. Alamdar Kapde Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026