MahaRERA Property Intelligence · Pune

CALLISTO

P51900017567 · Sion East · promoter Vibrant Homes Llp

Certificate SignedDue 01 Dec 2023

Delivery & Registration

MahaRERA registrationP51900017567
Registered on28 Aug 2018
Promoter-declared completion01 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vibrant Homes Llp is the promoter of record on 6 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
Callisto1G+2131 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202201 Dec 2023The said project is a MCGM Leasehold Plot wherein we first have to obtain Estate NOC from MCGM before applying for Occupation Certificate from Building Proposal Department of MCGM.

Location, Land & Connectivity

Located at Sion East, Flank Road, Ward GSouth, Mumbai City, 400022. Per the filed land record, the plot is bounded to the north by Chiman Niwas Plot No 253, to the south by Sunil Building Plot No 255, to the east by Road No 31A and to the west by Road No 32 Flank Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)122 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sion

Aadi Arpan
possession by Jul 2026 · Aadi Shikhar LLP
DNS Anuutham
possession by Aug 2026 · DNS Constructions Private Limited
Runwal Timeless
possession by Sep 2026 · Runwal Developers Limited
Harsh Tulip
possession by Oct 2026 · Harsh Developers & Infrastructure LL
Lodha NCP Tower - 1
possession by Dec 2026 · Lodha Developers Limited
Raunak Centrum
possession by Dec 2026 · Raunak Jigna Associates

Major developers building in Sion

Other RERA-registered projects in Mumbai City

Carmichael Residences
declared completion Sep 2019 · R A Realty Ventures LLP
Casa Celeste
declared completion Dec 2019 · Aster Developers
Casa Emerald
declared completion Dec 2022 · Hemali Investments & Finance Pvt.ltd
Ccil Bhavan
declared completion Jun 2026 · Suraj Estate Developers LTD
Ceejay Residency
declared completion Jun 2025 · Prime Realty LLP
Celestia Spaces
declared completion Dec 2022 · Peninsula Land Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026