MahaRERA Property Intelligence · Mumbai Suburban

Gokul Silvermist

P51800012140 · Santacruz (West) · promoter Heena Builders And

Certificate SignedDue 24 Jan 2024

Delivery & Registration

MahaRERA registrationP51800012140
Registered on01 Sep 2017
Promoter-declared completion24 Jan 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Heena Builders And is the promoter of record on 9 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Gokul Silvermist1G+830 Sep 2018

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000007881909/04/2019LEENA K. NISAR & KIRAN N. NISAR vs HEENA BUILDERS & DEVELOPERSorder passed
CC00600000022097330/04/2022Vinod Padmakant Parekh vs M/s Heena Builders & Developersorder passed
CC00600000022103330/04/2022Vinod Padmakant Parekh vs M/s Heena Builders and Developersorder passed
CC00600000022103530/04/2022Vinod Padmakant Parekh vs M/s Heena Builders and Developersorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
24 Jan 202430 Apr 2020Our Project is located in the corridor area which is between the western railway and s.v road. Due to corridor Location the mcgm only permits SLUM TDR. Thus due to the scarcity of
24 Jan 202430 Apr 2020Due to change in policy DCPR 1991 TO 2034. The File is rejected twice due to changes in DCPR 2034 like “width of staircase.”(As per DCPR 2034 width of staircase is compulsory requi
24 Jan 202424 Jul 2023The TDR has been purchased for the said project but unable to move ahead because of the suit in the said project. Due to this force majeure situation we would please ask the author

Location, Land & Connectivity

Located at Santacruz (West), Junction of Beseant and Sai baba Road, Andheri, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by FPNO 15 TPS I, to the south by EXISTING SAIBABA ROAD, to the east by EXISTING BESANT ROAD and to the west by FP NO 17A TPS I. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Gokul Vaibhav
declared completion Sep 2020 · Heena Lifestyles
Gold Leaf
possession by Dec 2029 · Shelaji Horizon LLP
Gold Residences
possession by Mar 2029 · Time & Jet Realty LLP
Goldcrest Business Park
declared completion Dec 2018 · Swastik Associates
Golden Casa
possession by Dec 2028 · Interlink Builders
Golden Gateway
possession by Dec 2029 · D.N Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026