30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700024141

Delivery and registration

When is the project declared for completion?

Jasmine L and M is registered with MahaRERA as P51700024141 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700024141
Registered on21 Jan 2020
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Jasmine L and M record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Palava Dwellers is the promoter of record on 86 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

86projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Jasmine L and M in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
Jasmine L1-30 Sep 2023
Jasmine M1-30 Sep 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Taloja, Kalyan Shil fata road, Mumbai City, Mumbai City, 421204. Per the filed land record, the plot is bounded to the north by 55 by 2 part and 55 by 5 part, to the south by 55 by 2 part and 55 by 5 part, to the east by 55 by 5 part and to the west by 55 by 2 part. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Palava Dwellers Pvt Ltd is the promoter on 6 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Palava Dwellers Pvt Ltd project & its RERA track record →

Other flagged projects by Palava Dwellers Pvt Ltd

Palava Dwellers Pvt Ltd
FlaggedThane
Palava Dwellers Pvt Ltd
Deregistered by MahaRERAThane

Other RERA-registered projects in Dombivali

Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons
Neelkamal Residency AND Business Park
possession by Dec 2026 · Neelkamal Buildco
Paramount
possession by Dec 2026 · Metro Dream Homes
Auroville Wing C AND D
possession by Dec 2026 · Arya Construction

Major developers building in Dombivali

Other RERA-registered projects in Thane

Jasmine T
declared completion Mar 2023 · Palava Dwellers Pvt Ltd
Jasper C And D
possession by Aug 2028 · Lodha Developers Limited
Jay Annapurna Co Operative Housing Society Ltd
possession by Dec 2027 · S M Enterprises
JAY Ganesh Darshan Chsl
possession by Dec 2026 · Yadav Bros Construction
JAY Meghdoot Chsl
possession by Sep 2026 · S R Developers
JAY Ramdarshan CHS LTD
possession by Nov 2026 · Mitra Buildcon

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026