MahaRERA Property Intelligence · Thane

KK RESIDENCY

P51700027183 · SHILL MUMBRA · promoter Realty

Certificate SignedDue 30 Jun 2026

Delivery & Registration

MahaRERA registrationP51700027183
Registered on24 Nov 2020
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
A11G+831 Dec 2025
A21G+831 Dec 2025
A31G+831 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SHILL MUMBRA, SHILL, Thane, Thane, 421204. Per the filed land record, the plot is bounded to the north by SNO 192 2, to the south by SNO 193, to the east by SNO 193 and to the west by SNO 192 3PT 60 MW DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivali

Balaji Estate
possession by Jul 2026 · M/s. Sai Balaji Buildcon
Jayram Heights
possession by Jul 2026 · Ashapura Enterprises
Pearl B
possession by Jul 2026 · Lodha Developers Limited
Runwal Gardens Phase 4 Bldg No. 33-34
possession by Sep 2026 · Runwal Residency Private Limited
Sai Siddhi Residency
possession by Sep 2026 · Devendra Damodar Patil
Alimkar Heights
possession by Oct 2026 · Alimkar & Sons

Major developers building in Dombivali

Other RERA-registered projects in Thane

KMC Skyline
possession by Jun 2028 · Prime Properties
Koel
declared completion Dec 2025 · Shree Shakti Developers
Kohinoor Aashiyana
declared completion Oct 2024 · KGI Realty Private Limited
Kohinoor Anaya
possession by Dec 2028 · KGI Realty Private Limited
Kohinoor Bella
possession by Dec 2029 · KGI Realty Private Limited
Kohinoor Castles
declared completion Mar 2021 · Kohinoor Castles

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026