MahaRERA Property Intelligence · Thane

LAABH ENCLAVE- PHASE 2

P51700011559 · BHIWANDI · promoter Vaishnavi

Certificate SignedDue 31 Mar 2023

Delivery & Registration

MahaRERA registrationP51700011559
Registered on31 Aug 2017
Promoter-declared completion31 Mar 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vaishnavi is the promoter of record on 75 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
LAABH ENCLAVE-PHASE 21G+1631 Mar 2020
LAABH ENCLAVE - PHASE D WING1G+1631 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 202330 Sep 2021As on date, we have already constructed 15 floors out of the total 15 floors in C Wing of the project named Laabh Enclave - Phase 2. However, due to the COVID 19 pandemic, the cons
31 Mar 202331 Mar 2023There was a dispute with the neighbouring plot which is now settled and now an application with planning authority for amendment of plan is submitted. After the approval of applica

Location, Land & Connectivity

Located at BHIWANDI, THEMGHAR ROAD, Mumbai, Mumbai Suburban, 421302. Per the filed land record, the plot is bounded to the north by 12-13, to the south by DP ROAD, to the east by 4 and to the west by 2-3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vaishnavi Housing Realty LLP is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Vaishnavi Housing Realty LLP project & its RERA track record →

Other flagged projects by Vaishnavi Housing Realty LLP

Vaishnavi Housing Realty LLP
Not filing quarterly progress reportsThane

Other RERA-registered projects in Bhiwandi

Neelkanth Sadan
possession by Jul 2026 · Shreeji Enterprises
Hill Spring
possession by Aug 2026 · Asha Infratech
Nazir Heights
possession by Sep 2026 · A M Constructions
Rose Residency
possession by Sep 2026 · Kunal Ramesh Karaniya
Saniya Heights
possession by Sep 2026 · Moonshine Realtors PVT LTD
Upper Thane-Casa Eden
possession by Sep 2026 · Lodha Developers Limited

Major developers building in Bhiwandi

Other RERA-registered projects in Thane

Laabh Enclave Phase 2 D Wing
possession by Mar 2027 · Vaishnavi Housing Realty LLP
Laabh Gloria
declared completion Dec 2025 · Laabh Buildwell
Laabh Neelkanth
declared completion Dec 2019 · Laabh Buildtech
Laaman Industrial Park
declared completion Jan 2025 · Laaman Developers
Lake Emerald- Phase I
possession by Apr 2027 · N D Enterprises
Lake View
declared completion Dec 2024 · SAI Mahima Infradevelopers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.