Mumbai/Project record

MahaRERA · the public record

Landmark

L Ward · Aahana Expert Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

45units filed as unsoldInventory · 20 September 2026
31 Dec 2032declared completionMahaRERA registration · read 02 Jul 2026
58registered unitsMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2032

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1180002502911

Delivery and registration

When is the project declared for completion?

Landmark is registered with MahaRERA as PM1180002502911 and the promoter has declared completion for 31 Dec 2032.

31 Dec 2032

declared completion

75months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPM1180002502911
Registered on18 Mar 2026
Promoter-declared completion31 Dec 2032
Current statusCertificate Signed
Against today75 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Landmark record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In Landmark, 0 of 45 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 45 remain available.

0%sold

0 of 45 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 58 homes in total, while this sold/unsold inventory filing covers 45 of them.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Landmark in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in Landmark carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 45 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 4,874 a sq ft typical, over Rs 4,873 to Rs 4,874.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 45 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 45 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 58 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Landmark1G+1658-

Unit mix on the filing: 49 residential and 9 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Landmark, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 02 Jul 2026

Complaint no.FiledPartiesStatus
SM1260032212/05/2026Bhakti Achrekar vs Aahana Expert Homesorder passed

Location, Land & Connectivity

Located at L Ward, V. N. Purav Marg, Mumbai City, Mumbai City, 400022. Per the filed land record, the plot is bounded to the north by V. N. Purva Marg and C.T.S No. 419, to the south by D.P. Road and C.T.S No. 451, to the east by C.T.S Nos. 419, 420, 421, 450 and 451 and to the west by V. N. Purva Marg and D.P. Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Lower Parel / Worli business district7 km
Powai / Hiranandani business park8 km
Andheri MIDC / SEEPZ9 km
Nariman Point / Fort15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sion

Runwal Timeless
possession by Sep 2026 · Runwal Developers Limited
Harsh Tulip
possession by Oct 2026 · Harsh Developers & Infrastructure LL
Lodha NCP Tower - 1
possession by Dec 2026 · Lodha Developers Limited
Raunak Centrum
possession by Dec 2026 · Raunak Jigna Associates
Shankesh Crown
possession by Dec 2026 · H. Mehta Realtors LLP
Shreeji Palazzo
possession by Dec 2026 · Excellent Enterprise

Major developers building in Sion

Other RERA-registered projects in Mumbai Suburban

Lashkaria Anurag
declared completion Aug 2019 · Lashkaria Housing & Infrastructure P
Lashkaria Indrasukh
possession by Dec 2028 · Lashkaria Housing & Infrastructure L
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
Lashkaria Solitaire
possession by Oct 2027 · Relliance Realty
Lawns And Beyond - Phase 1, Omkar International District
declared completion Mar 2026 · Omkar Ventures Pvt. Ltd.
Lawns And Beyond - Phase 2, Omkar International District
possession by Mar 2027 · Omkar Ventures Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026