MahaRERA Property Intelligence · Mumbai Suburban

MANDOR LEELA

P51800033097 · GOREGAON WEST · promoter Krs Infrastructure Private

Certificate SignedDue 31 Mar 2025

Delivery & Registration

MahaRERA registrationP51800033097
Registered on09 Feb 2022
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Mandor Leela1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at GOREGAON WEST, CTS 202 FINAL PLOT NO. 102, 103 ROAD NO. 06 , Mumbai, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by CTS 203, to the south by CTS 201, to the east by CTS 199 AND CTS 200 and to the west by L T NAGAR ROAD NO 6. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon West

Giriraj
possession by Jul 2026 · Parshva Associates
Sejal Kajal Apartment CHS LTD
possession by Jul 2026 · Neminath Realtors
Goregaon Vihar Darshan CHS LTD
possession by Aug 2026 · Silver Lifespaces Private Limited
Atria Arshabharat
possession by Aug 2026 · Dharti Aakar Realty
Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Sahakar Revanta
possession by Sep 2026 · Sahakar Builders & Developers

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Maneesha Chsl
declared completion Dec 2019 · Shah Developers
Manek Terrace CHS LTD
declared completion Oct 2020 · K T Group
Mangal Business Park - Gautam Apartment
possession by Mar 2027 · Mangal Buildhome Private Limited
Mangal Meeth CHS LTD
declared completion Dec 2025 · Aspen Real Estate Developers LLP
Mangal Smriti
declared completion Jun 2022 · Mangal Buildhome Private Limited
Mangal Varsha
declared completion May 2026 · Rishabraj Namo Enterprise LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026