MahaRERA Property Intelligence · Mumbai Suburban

Kalpataru Radiance E

P51800013245 · promoter Keyana Estate Llp

Certificate SignedDue 30 Jun 2022

Delivery & Registration

MahaRERA registrationP51800013245
Registered on21 Sep 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Keyana Estate Llp is the promoter of record on 5 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~89.7% of the estimated project cost incurred as of the last certificate (₹6.61 Cr spent against a ₹7.37 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~89.7% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.

BuildingWingsFloorsDeclared completion
Retail Zone I1G+031 Dec 2021
Retail Zone II1G+031 Dec 2021
Retail Zone III1G+0-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High CourtSuit Lodging No 1762018Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202230 Jun 2023We hereby submit for your kind advice and guidance in the matter: Kiyana Ventures LLP (Promoter) is a promoter of the real estate projects namely Kalpataru Radiance E (Project)

Location, Land & Connectivity

Located at Goregoan, Andheri, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by CTS No- 260-6 being part of existing road, to the south by CTS No 260-4 being part of existing road, to the east by CTS No- 260-5B being part of existing road and to the west by Existing Nala. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport8 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district18 km
Nariman Point / Fort26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Keyana Estate LLP is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Keyana Estate LLP

Keyana Estate LLP
FlaggedMumbai Suburban
Keyana Estate LLP
FlaggedMumbai Suburban
Keyana Estate LLP
FlaggedMumbai Suburban
Keyana Estate LLP
FlaggedMumbai Suburban

Other RERA-registered projects in Goregaon West

Giriraj
possession by Jul 2026 · Parshva Associates
Sejal Kajal Apartment CHS LTD
possession by Jul 2026 · Neminath Realtors
Goregaon Vihar Darshan CHS LTD
possession by Aug 2026 · Silver Lifespaces Private Limited
Atria Arshabharat
possession by Aug 2026 · Dharti Aakar Realty
Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Sahakar Revanta
possession by Sep 2026 · Sahakar Builders & Developers

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Kalpataru Solitaire
declared completion Dec 2019 · Kalpataru Limited
Kalpataru Summit
possession by Jun 2027 · Arimas Real Estate Private Limited
Kalpataru Verbina
possession by Dec 2029 · Kalpataru Shubham Enterprises
Kalpataru Vienta Tower A
possession by Jun 2027 · Kalpataru Retail Ventures Private Limite
Kalpataru Vienta Tower B
possession by Dec 2026 · Kalpataru Retail Ventures Private Limite
Kalpataru Virtus
possession by Dec 2029 · Mehal Enterprise LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026