30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900005130

Delivery and registration

When is the project declared for completion?

S R SCHEME AT RAHUL NAGAR, SEWREE is registered with MahaRERA as P51900005130 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900005130
Registered on09 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for S R SCHEME AT RAHUL NAGAR, SEWREE record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shivshahi Punarvasan Prakalp is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for S R SCHEME AT RAHUL NAGAR, SEWREE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SALE BUILDING NO 21G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Sewri, Andheri, Mumbai Suburban, 400015. Per the filed land record, the plot is bounded to the north by BUILDING NO 7, to the south by ARYA HONDA GARAGE, to the east by 65 FEET WIDE SEWREE ROAD and to the west by SALE BUILDING NO 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~103 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park103 km
Baner–Balewadi belt109 km
Pune Junction / city centre119 km
Pune Int'l Airport (Lohegaon)121 km
Kharadi / EON IT Park125 km
Magarpatta / Hadapsar IT125 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shivshahi Punarvasan Prakalp LTD is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shivshahi Punarvasan Prakalp LTD

Shivshahi Punarvasan Prakalp LTD
Past its declared completion dateMumbai City

Other RERA-registered projects in Sewri

Avenue 15
possession by Sep 2026 · Ramesh Barrel Supplying Co
J K Apartment
possession by Dec 2026 · Plus Properties PVT LTD
The Gateway
possession by Sep 2028 · LH Residential Housing Private Limited
Aqua BAY
possession by Dec 2028 · Chamunda Infrastructure Limited
The Royal Oaks Residency
possession by Dec 2030 · Mighty Oaks Constructions LLP
Lodha Sewri Project
possession by Dec 2032 · Lodha Developers Limited

Major developers building in Sewri

Other RERA-registered projects in Mumbai City

S3 Epitome
possession by Dec 2028 · S3 Smart Spaces Private Limited
Sach Vintage
possession by Dec 2026 · Ushadevi Vijaykumar Chandan
Sadhanaa Building
declared completion Oct 2023 · Sidaan Enterprise
Saffron
possession by Dec 2028 · Buildarch - GP
Safiya Heights
declared completion Dec 2025 · SMY Associates
SAI Ekvira Sadan
declared completion Dec 2021 · K Merchant Construction Ltd

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.