MahaRERA Property Intelligence · Mumbai Suburban

SEASONS PREM SAGAR

P51800078579 · SANTACRUZ WEST · promoter Enterprise

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51800078579
Registered on27 Dec 2024
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
SEASONS PREM SAGAR1G+18-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SANTACRUZ WEST, JUNCTION OF VALLABHAI PATEL ROAD AND JK MEHTA ROAD, Andheri, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by SANTACRUZ POLICE STATION QUARTERS, to the south by JK MEHTA ROAD, to the east by PLOT NO 60 BALAJI TOWERS and to the west by V P ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8205 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort8203 km
Lower Parel / Worli business district8205 km
Chhatrapati Shivaji Int'l Airport8209 km
Bandra Kurla Complex (BKC)8210 km
Andheri MIDC / SEEPZ8210 km
Powai / Hiranandani business park8214 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

D S Enterprise is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by D S Enterprise

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Seasons Trimurti
declared completion Dec 2025 · Seasons Avenues Properties
Seasons- Wing F
possession by Dec 2028 · Joynest Premises Private Limited
Second Avenue Phase 1
declared completion Dec 2025 · Atul Projects Realty Private Limited
Sector R 3 Mhada
declared completion Dec 2017 · Guruashish Construction Private Limited
Sector R-3 Of Siddhartha Nagar Patra Chawl Redevelopment
possession by Mar 2027 · Mumbai Housing And Area Development Boar
Seema Rajdhani
declared completion Sep 2025 · Seema Properties AND Builders LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026