Mumbai/Project record

MahaRERA · the public record

SHREE SHIVANKAR CHS

MATUNGA · ARTH REALTECH SPACES PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

10 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900020051

Delivery and registration

When is the project declared for completion?

SHREE SHIVANKAR CHS is registered with MahaRERA as P51900020051 and the promoter has declared completion for 10 Jun 2023.

10 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900020051
Registered on25 Mar 2019
Promoter-declared completion10 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE SHIVANKAR CHS record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Arth Realtech Spaces is the promoter of record on 27 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

27projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE SHIVANKAR CHS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Shree Shivankar CHS1G+2310 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High CourtSUIT/1012848/20162016Case Withdrawn And Settled
High CourtSUIT/0102848/20162016Case Withdrawn And Settled
High CourtSUIT/0102805/20162016Case Withdrawn And Settled
High CourtSUIT/0102806/20162016Case Withdrawn And Settled
High CourtSUIT/0102847/20162016Case Withdrawn And Settled
High Court2806/2805/2847/28482016Dismissed

Location, Land & Connectivity

Located at MATUNGA, TELANG ROAD, Ward GSouth, Mumbai City, 400022. Per the filed land record, the plot is bounded to the north by TELANG ROAD NO 3, to the south by BUILDING CS 358 10, to the east by BUILDING CS 359A 10 and to the west by TELANG ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sion

Runwal Timeless
possession by Sep 2026 · Runwal Developers Limited
Harsh Tulip
possession by Oct 2026 · Harsh Developers & Infrastructure LL
Lodha NCP Tower - 1
possession by Dec 2026 · Lodha Developers Limited
Raunak Centrum
possession by Dec 2026 · Raunak Jigna Associates
Shankesh Crown
possession by Dec 2026 · H. Mehta Realtors LLP
Shreeji Palazzo
possession by Dec 2026 · Excellent Enterprise

Major developers building in Sion

Other RERA-registered projects in Mumbai City

Shree Siddhi
possession by Dec 2026 · Vilas Ashok Chaudhari
Shree Swami Samartha Darshan
declared completion Dec 2021 · Shree Sai Datta Developers
Shree Udyan
possession by Dec 2026 · Square Nine Habitats LLP
Shree Vigneshwar CO-Operative Housing Society
declared completion Dec 2021 · Bineeta
Shreeji Heights
possession by Dec 2030 · Anupam Creation
Shreeji Palazzo
possession by Dec 2026 · Excellent Enterprise

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026