Siddhivinayak Tower

Mumbai Suburban · Lotus Realty

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900007562

Delivery and registration

When is the project declared for completion?

Siddhivinayak Tower is registered with MahaRERA as P51900007562 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900007562
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Siddhivinayak Tower record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Lotus Realty is the promoter of record on 50 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

50projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Siddhivinayak Tower in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Sea Breeze1G+2331 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400037. Per the filed land record, the plot is bounded to the north by 30 mtr DP Road, to the south by Anand Nagar CHS, to the east by 9 Mtr Saltpan Road and to the west by Rajiv Gandhi Nagar. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Lower Parel / Worli business district5 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ12 km
Nariman Point / Fort12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wadala East

Nisarg CO Operative Housing Society Limited
possession by Dec 2026 · Cosmos Landmarks
Siddha Sky Phase 2
possession by Dec 2026 · M/s Sejal Shakti Realtors LLP
Siddha Sky Phase 3
possession by Dec 2026 · M/s. Sejal Shakti Realtors LLP
Building NO 6 Ajmera Greenfinity A Wing B Wing
possession by May 2027 · Ajmera Realty AND Infra India LTD
Ajmera Manhattan Building 3A AND 3B
possession by Jun 2027 · Ajmera Realty AND Infra India LTD
Dosti Eastern BAY - Phase 3
possession by Sep 2027 · Dosti Realty LTD

Major developers building in Wadala East

Other RERA-registered projects in Mumbai City

Siddhivinayak Vastu
declared completion Dec 2018 · Siddhivinayak Construction Private Limit
Sidheshwar Royale
declared completion Mar 2026 · M/S YUG Developers
Sigma Garnet
possession by Dec 2026 · Colo Color Private Limited
Signare
possession by Sep 2026 · Tejukaya Buildcon
Signature
possession by Dec 2026 · Prabhat Sadan Properties Private Limited
Sila Tower
possession by Dec 2031 · Sila Offices Private Limiited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.