Mumbai/Project record

MahaRERA · the public record

Snehadeep Co-Operative Housing Society Ltd

Naupada · JOSHI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700013473

Delivery and registration

When is the project declared for completion?

Snehadeep Co-Operative Housing Society Ltd is registered with MahaRERA as P51700013473 and the promoter has declared completion for 31 Jul 2018.

31 Jul 2018

declared completion

98months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700013473
Registered on07 Oct 2017
Promoter-declared completion31 Jul 2018
Current statusCertificate Signed
Against todayabout 98 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Snehadeep Co-Operative Housing Society Ltd record 4 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Joshi Enterprises is the promoter of record on 98 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

98projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Snehadeep Co-Operative Housing Society Ltd in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Snehadeep Co-Operative Society Ltd1G+831 Jul 2018

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Snehadeep Co-Operative Housing Society Ltd, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007845113/03/2019SHRADDHA JOSHI vs Joshi Enterprisesorder passed
CC00600000019237331/01/2020SHRADDHA N JOSHI vs M/S JOSHI ENTERPRISESorder passed
CC00600000019431105/10/2020SHRADDHA NANDKUMAR JOSHI vs M/s Joshi Enterprisesorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
CivilRCS 347/152015Pending
CivilRCS 380/152015Pending
DistrictMCA 229/152015Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2018Project got slightly delayed due to main road concreting work being undertaken by TMC. This affected material movement on the site. Also project litigations have consumed a lot of

Location, Land & Connectivity

Located at Naupada, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by Mohan Gupte Bunglow, to the south by Pragat Society, to the east by High Wall of Graveyard and to the west by Maharshi Karve Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ13 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Joshi Enterprises is the promoter on 11 MahaRERA-registered projects, of which 8 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Joshi Enterprises project & its RERA track record →

Other flagged projects by Joshi Enterprises

Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Not filing quarterly progress reportsThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Past its declared completion dateThane
Joshi Enterprises
Past its declared completion dateThane

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Sneham
declared completion Sep 2025 · Paridhi Developers
Snehbandhan CHS
declared completion Sep 2020 · Ayushi Infra Enterprise Private Limited
Snehkiran Tower
possession by May 2027 · Snehkiran Buildcon Private Limited
Soham Neel
possession by Mar 2027 · M/s Neel Siddhi Enterprises
Soham Residency
declared completion Mar 2026 · Soham Construction
Sohum Heights
possession by Dec 2026 · M/S Sohum Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026