MahaRERA Property Intelligence · Mumbai City

SPACE RESIDENCY

P51900029581 · Byculla · promoter Space Builders

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51900029581
Registered on04 Jun 2021
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+31.

BuildingWingsFloorsDeclared completion
Space Residency1G+3131 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Byculla, Huzaria Street, Ward E, Mumbai City, 400008. Per the filed land record, the plot is bounded to the north by Dimtimkar Road, to the south by Huzaria Street, to the east by Mastan Talao Junction and to the west by Trimurti Building. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Byculla

Kings Tower
possession by Sep 2026 · Mohammed Eshaq ALI Vadgama
Shelaji Avenues
possession by Dec 2026 · Ashirwad Shelaji Developers LLP
Al - Haram Residency
possession by Dec 2026 · M/s K. S. Hind Developers
Baug E Umar
possession by Dec 2026 · Mahanagar Constructions Private Limited
Golden Residency
possession by Dec 2026 · Golden Realty
Lakadawala Heights
possession by Dec 2026 · Aariaash Developers

Major developers building in Byculla

Other RERA-registered projects in Mumbai City

Spee Skytower Wing A And B
declared completion Mar 2024 · Spee Realtor
Spenta Nest
possession by Dec 2028 · Shubh Enterprises
Splendour
possession by Mar 2027 · Netra Developers
Spring Dale
declared completion Sep 2018 · Sunrise Associates
SSG Springville
declared completion Dec 2024 · Itmc Developers Pvt. Ltd.
ST Anthony Apartment
declared completion Sep 2020 · Suraj Estate Developers LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026