MahaRERA Property Intelligence · Palghar
P99000029193 · KHANIVALI · promoter Herambh Developers
| MahaRERA registration | P99000029193 |
| Registered on | 03 May 2021 |
| Promoter-declared completion | 31 Dec 2028 |
| Current status | Certificate Signed |
| Against today | 29 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~67.3% of the estimated project cost incurred as of the last certificate (₹3.24 Cr spent against a ₹4.82 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 62 homes filed with MahaRERA, 27 are sold/booked and 35 remain available (~44% sold) — selling steadily. Buyers have committed ₹3.03 Cr in agreement value so far. Of that, ₹3.03 Cr (~100%) is already collected, ₹0 receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 27 registered agreements, the effective carpet rate is ₹3,855/sqft (typical range ₹2,705–₹4,492) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 1 | A-101 | 462 sqft (42.93 sqm) | ₹13.70 Lakh |
| Floor 1 | A-102 | 462 sqft (42.93 sqm) | ₹13.70 Lakh |
| Floor 1 | A-103 | 633 sqft (58.82 sqm) | ₹18.78 Lakh |
| Floor 1 | A-104 | 503 sqft (46.75 sqm) | ₹14.92 Lakh |
| Floor 1 | B-204 | 481 sqft (44.7 sqm) | ₹14.27 Lakh |
| Floor 1 | B-304 | 481 sqft (44.7 sqm) | ₹14.27 Lakh |
| Floor 1 | C-101 | 503 sqft (46.75 sqm) | ₹14.92 Lakh |
| Floor 1 | C-102 | 633 sqft (58.82 sqm) | ₹18.78 Lakh |
| Floor 1 | C-103 | 557 sqft (51.76 sqm) | ₹16.52 Lakh |
| Floor 1 | C-104 | 667 sqft (61.99 sqm) | ₹19.79 Lakh |
| Floor 2 | A-201 | 462 sqft (42.93 sqm) | ₹13.70 Lakh |
| Floor 2 | A-202 | 462 sqft (42.93 sqm) | ₹13.70 Lakh |
| Floor 2 | A-203 | 633 sqft (58.82 sqm) | ₹18.78 Lakh |
| Floor 2 | A-204 | 503 sqft (46.75 sqm) | ₹14.92 Lakh |
| Floor 2 | B-104 | 481 sqft (44.7 sqm) | ₹14.27 Lakh |
| Floor 2 | C-201 | 503 sqft (46.75 sqm) | ₹14.92 Lakh |
| Floor 2 | C-202 | 633 sqft (58.82 sqm) | ₹18.78 Lakh |
| Floor 2 | C-203 | 557 sqft (51.76 sqm) | ₹16.52 Lakh |
| Floor 2 | C-204 | 667 sqft (61.99 sqm) | ₹19.79 Lakh |
| Floor 3 | A-301 | 462 sqft (42.93 sqm) | ₹13.70 Lakh |
| Floor 3 | A-302 | 462 sqft (42.93 sqm) | ₹13.70 Lakh |
| Floor 3 | A-303 | 633 sqft (58.82 sqm) | ₹18.78 Lakh |
| Floor 3 | A-304 | 503 sqft (46.75 sqm) | ₹14.92 Lakh |
| Floor 3 | C-301 | 503 sqft (46.75 sqm) | ₹14.92 Lakh |
| Floor 3 | C-302 | 633 sqft (58.82 sqm) | ₹18.78 Lakh |
| Floor 3 | C-303 | 557 sqft (51.76 sqm) | ₹16.52 Lakh |
| Ground/Floor 0 | Shop -07 | 185 sqft (17.19 sqm) | ₹7.78 Lakh |
| Ground/Floor 0 | Shop-08 | 231 sqft (21.47 sqm) | ₹9.71 Lakh |
| Ground/Floor 0 | Shop-10 | 185 sqft (17.19 sqm) | ₹7.78 Lakh |
| Ground/Floor 0 | Shop-11 | 208 sqft (19.33 sqm) | ₹8.74 Lakh |
| Ground/Floor 0 | Shop-13 | 214 sqft (19.89 sqm) | ₹9.00 Lakh |
| Ground/Floor 0 | Shop-14 | 313 sqft (29.09 sqm) | ₹13.16 Lakh |
| Ground/Floor 0 | Shop-16 | 410 sqft (38.1 sqm) | ₹17.24 Lakh |
| Ground/Floor 0 | shop -05 | 231 sqft (21.47 sqm) | ₹9.71 Lakh |
| Ground/Floor 0 | shop-09 | 231 sqft (21.47 sqm) | ₹9.71 Lakh |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 62 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| STAR COMPLEX | 1 | G+3 | 62 | 31 Dec 2023 |
Unit mix on the filing: 62 residential.
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Dec 2023 | 31 Dec 2024 | Date: 12th January, 2024 To, The Maharashtra Real Estate Regulatory Authority (RERA) Mumbai Dear Sir/Madam, Sub: Application for Extension of Project U/S 7(3) Ref: S |
| 31 Dec 2023 | 31 Dec 2028 | Respected Sir / maam We hereby apply for Revision of Plan Star Complex registered with the regulatory authority vide project registration certificate bearing No. P99000029193. In t |
Located at KHANIVALI, KHANIVALI, Vada, Palghar, 421204. Per the filed land record, the plot is bounded to the north by GUT NO 393, to the south by GUT NO 439, to the east by GUT NO 393 and to the west by 24 MTR WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Bandra Kurla Complex (BKC) | 2 km |
| Chhatrapati Shivaji Int'l Airport | 2 km |
| Powai / Hiranandani business park | 5 km |
| Andheri MIDC / SEEPZ | 6 km |
| Lower Parel / Worli business district | 10 km |
| Nariman Point / Fort | 18 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in STAR COMPLEX?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026