SUNSHINE GREEN PARK PHASE I

VASAI EAST · SHantee Homes Realty LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000001370

Delivery and registration

When is the project declared for completion?

SUNSHINE GREEN PARK PHASE I is registered with MahaRERA as P99000001370 and the promoter has declared completion for 31 Mar 2018.

31 Mar 2018

declared completion

102months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000001370
Registered on27 Jul 2017
Promoter-declared completion31 Mar 2018
Current statusCertificate Signed
Against todayabout 102 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUNSHINE GREEN PARK PHASE I record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shantee Homes Realty is the promoter of record on 31 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SUNSHINE GREEN PARK PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SUNSHINE GREEN PARK BLDG No 031G+431 Mar 2018
SUNSHINE GREEN PARK BLDG N0 041G+431 Mar 2018
SUNSHINE GREEN PARK BLDG No 051G+1-
SUNSHINE GREEN PARK BLDG No 011G+831 Mar 2018
SUNSHINE GREEN PARK BLDG No 021G+431 Mar 2018

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for SUNSHINE GREEN PARK PHASE I, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005602131/08/2018Vikas Dhondiram Sapkal vs M/S Shantee Homes Realty LLPorder passed
CC00600000014120428/10/2019Jayprakash Pal vs Shantee Homes Realty LLPorder passed
CC00600000017173306/12/2019Prashant Desai vs Shantee Homes Reality LLPorder passed
CC00600000019829013/09/2021Sunshine Green Park Building No.2, 3 & 4CHS Ltd vs M/s Shanti Homes Realty LLP Through Partner 1.Niyaz S.Pathan 2. Raaz abdul Samad Pathanorder passed

Location, Land & Connectivity

Located at VASAI EAST, GOKHIVARE, Vasai, Palghar, 401208. Per the filed land record, the plot is bounded to the north by Open plot, to the south by Huts, to the east by Open plot and Huts and to the west by Future building. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ31 km
Powai / Hiranandani business park33 km
Chhatrapati Shivaji Int'l Airport36 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district46 km
Nariman Point / Fort54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shantee Homes Realty LLP is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Shantee Homes Realty LLP project & its RERA track record →

Other flagged projects by Shantee Homes Realty LLP

Shantee Homes Realty LLP
FlaggedPalghar
Shantee Homes Realty LLP
FlaggedPalghar
Shantee Homes Realty LLP
FlaggedPalghar
Shantee Homes Realty LLP
FlaggedPalghar
Shantee Homes Realty LLP
FlaggedPalghar

Other RERA-registered projects in Vasai East

AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP
Matoshri Heights
possession by Oct 2026 · Nagesh Hemant Patil
Hayaat Galaxy II
possession by Nov 2026 · M M Enterprises
Apeksha Complex
possession by Dec 2026 · Kothari Construction CO

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Sunshine Green Park Phase V
declared completion Dec 2025 · Shantee Homes Realty LLP
Sunshine Meadows
possession by Dec 2030 · Shantee Global Realty LLP
Sunshine Plaza
possession by Dec 2028 · Sunrise Homes
Sunshine Residency
possession by Dec 2027 · Raaz Mohammad Abdul Samad Pathan
Sunshine Sapphire
declared completion Nov 2020 · Shantee Housing
Sunshine Sapphire
declared completion Dec 2024 · Shantee Housing

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026