THE ADHIRAJ

SANTACRUZ (WEST) · SAGAR MANOJ GORADIA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

5units filed as unsoldInventory · 20 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
24registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800079982

Delivery and registration

When is the project declared for completion?

THE ADHIRAJ is registered with MahaRERA as P51800079982 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800079982
Registered on09 Apr 2025
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Promoter record

What else is this promoter on record for?

Sagar Manoj Goradia is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In THE ADHIRAJ, ₹5.60 Cr of a declared ₹10.21 Cr estimated project cost is reported as incurred, about 54.9%, as at the last certified filing with MahaRERA.

54.9%

₹5.60 Cr

of ₹10.21 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In THE ADHIRAJ, 4 of 9 homes filed with MahaRERA are recorded as sold or booked, about 44%, and 5 remain available.

44%sold

4 of 9 homes

₹12.05 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹7.36 Cr (about 61%) is recorded as collected and ₹4.69 Cr as receivable. The project registers 24 homes in total, while this sold/unsold inventory filing covers 9 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101291 sqft (27.07 sqm)₹76.23 Lakh
Floor 111102169 sqft (15.74 sqm)₹1.04 Cr
Floor 121202169 sqft (15.74 sqm)₹1.04 Cr
Floor 22011,081 sqft (100.44 sqm)₹2.83 Cr
Floor 88011,081 sqft (100.44 sqm)₹2.83 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for THE ADHIRAJ in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 4 homes carry one, and 5 of the 9 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
2011,081 sqftRs 3.4600 cr typical, over Rs 3.4500 cr to Rs 3.4600 cr3 filed on this stack, floors 5–9

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 24 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
THE ADHIRAJ1G+1324-

Unit mix on the filing: 24 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SANTACRUZ (WEST), PODDAR ROAD, Andheri, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by FP NO 41 HARIHAR NIWAS, to the south by FP NO 43 ARCADE AURA, to the east by FP NO 47 MANGAL NURSING HOME and to the west by DP ROAD PODDAR ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sagar Manoj Goradia is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

THE Alka CO-Operative Housing Society Limited
possession by Apr 2027 · THE Alka CO-Operative Housing Society Li
THE Altezza
possession by Jun 2029 · M/s. Vipl Varasiddhi Infra Project LLP
The Altimus
possession by Sep 2029 · Sosar Corporation LLP
The Arcade
declared completion Jun 2025 · CCI Projects Private Limited
THE Arcadian
possession by Dec 2027 · Dhyan Projects Private Limited
The Baya Junction
declared completion Dec 2023 · M/s. Unique Property Enterprises Pvt. Lt

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026