Mumbai/Project record

MahaRERA · the public record

The Baya Junction

Pestom Sagar · M/s. Unique Property Enterprises Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800015307

Delivery and registration

When is the project declared for completion?

The Baya Junction is registered with MahaRERA as P51800015307 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800015307
Registered on15 Feb 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for The Baya Junction record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Unique Property Enterprises is the promoter of record on 133 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

133projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for The Baya Junction in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
The Baya Junction1G+2231 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for The Baya Junction, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019679828/04/2021Puneet Kalwani vs M/s Unique Property Enterprises Private Limitedorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court1688/20162016Closed
Additional Chief Metropolitan Magistrate182011Closed

Location, Land & Connectivity

Located at Pestom Sagar, Pestom Sagar rd no 6, Ward GSouth, Mumbai City, 400089. Per the filed land record, the plot is bounded to the north by Somaiya Nalla, to the south by D P Road, to the east by Slum and to the west by Slum. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park5 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district11 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Orient Regency Building No. 1
possession by Dec 2026 · Orient Combine
Sree Sudarshan Heights
possession by Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
possession by Dec 2026 · Chinnaiah Venkatesh Gowda
Promesa Midtown
possession by Dec 2026 · Darshan Properties
Vishwasangam
possession by Dec 2026 · Vishwashakti Cooperative Housing Society
Ampple-ONE
possession by Mar 2027 · Amppletech Projects Private Limited

Other RERA-registered projects in Mumbai Suburban

The Baya Sanctum
possession by Jun 2028 · Lodha Developers Limited
THE Bliss
declared completion Jun 2024 · SBM Realtors PVT LTD
THE Borivali Neel Akash Chsl
declared completion Dec 2018 · Triveni Developers
The Business Hub
declared completion Dec 2025 · Ankur Mayflower Associates
THE Capital
possession by Dec 2027 · ANS Lifestyle Realtors LLP
THE Castle
possession by Aug 2027 · Solidago Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026