TRIDHAATU BHAVESHWAR VILAS

P51800002054 · Chembur · promoter Tridhaatu Bhaveshwar Developers

Certificate SignedDue 29 Dec 2024

Delivery & Registration

MahaRERA registrationP51800002054
Registered on31 Jul 2017
Promoter-declared completion29 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tridhaatu Bhaveshwar Developers is the promoter of record on 17 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Tridhaatu Bhaveshwar Vilas1G+1531 Dec 2022

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260179928/03/2026Krishnan Raman Iyer vs TRIDHAATU BHAVESHWAR DEVELOPERS LLPpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202429 Dec 2024The Project Building ‘Tridhaatu Bhaveshwar Vilas comprises of Ground + 13 floors. Work to date has been completed in accordance with the current approvals in place. The said Proje

Location, Land & Connectivity

Located at Chembur, 17th Road, Kurla, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by Road, to the south by CTS No 934 and 937, to the east by CTS No 936 and to the west by CTS No 930. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Tridhaatu Morya
declared completion Dec 2025 · Tridhaatu Morya Developers PVT LTD
Tridhaatu Morya II
declared completion Dec 2025 · Tridhaatu Morya Developers PVT LTD
Tridhaatu Morya III
declared completion Dec 2025 · Tridhaatu Morya Developers PVT LTD
Tridhaatu Prarambh
declared completion Mar 2024 · Panch Tatva Realty
Tridhaatu Shobha Aayu
declared completion Dec 2023 · Tridhaatu Maruti Developers LLP
Trienity 1 Phase II
possession by Mar 2027 · Trienity Prime Property Projects LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.