Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51700035166
Registered on10 May 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tycoons Avanti Projects is the promoter of record on 9 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35.

BuildingWingsFloorsDeclared completion
Tower D1G+35-

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260413102/07/2026Amol Anant Kadam vs Tycoons Avanti Projects LLPpending / no order on file
CC1240041214/10/2024Anand Sharma vs Tycoons Avanti Projects LLPorder passed
CC1250394210/11/2025Prakash Arvind Pedenkar vs Tycoons Avanti Projects LLPorder passed

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil CourtRCS No 3162016Pending
Appellate CourtMCA No 362017Pending
High Court Of BombayWP No 108922017Pending
Civil JudgeRCS NO.316/20162016Ongoing
Judicial Magistrate First ClassSCC NO. 2188/20232023Ongoing
Civil JudgeSCS NO. 142/20252025Ongoing

Location, Land & Connectivity

Located at Konkan Vasahat, Birla College Road, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by NH 222, to the south by S No 20, to the east by 15 MTR Wide DP Road and to the west by 6 MTR Wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~27 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park27 km
Andheri MIDC / SEEPZ30 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district41 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tycoons Avanti Projects Pvt. Ltd. is the promoter on 7 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Tycoons Avanti Projects Pvt. Ltd.

Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane
Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane
Tycoons Avanti Projects Pvt. Ltd.
Not filing quarterly progress reportsThane
Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane
Tycoons Avanti Projects Pvt. Ltd.
Not filing quarterly progress reportsThane
Tycoons Avanti Projects Pvt. Ltd.
FlaggedThane

Other RERA-registered projects in Kalyan

Tharwani Solitaire Phase IV
possession by Jul 2026 · Anil Hardasmal Tharwani
Kailash Gardens
possession by Jul 2026 · Shree Laxmi Enterprises
Mangeshi Ambar
possession by Jul 2026 · Mangesh Dashrath Gaikar
Mangeshi Tulip
possession by Jul 2026 · Mangesh Dashrath Gaikar
Anand 21 Uptown
possession by Aug 2026 · VPA Developers
Pawan Atharva Phase I
possession by Aug 2026 · Pawan Real Estate

Major developers building in Kalyan

Other RERA-registered projects in Thane

Tycoons Valley Tower A
declared completion Dec 2025 · M/s. Milestone Space
Tycoons Valley Tower B
declared completion Jun 2025 · M/s. Milestone Space
Type-B Redwood
declared completion Dec 2022 · RDC Ventures
Udaynagar Chs
possession by Mar 2028 · Natu Paranjape Realty
UMA Ananta
possession by Mar 2029 · UMA Infratech
Uma Ashish A Wing
declared completion Dec 2019 · Uma Housing

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.