MahaRERA Property Intelligence · Mumbai Suburban

UNIQUE AURA

P51800051237 · Santacruz West · promoter Unique Shanti Developers

Certificate SignedDue 31 Mar 2026

Delivery & Registration

MahaRERA registrationP51800051237
Registered on08 Jun 2023
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Unique Shanti Developers is the promoter of record on 129 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~64.4% of the estimated project cost incurred as of the last certificate (₹14.68 Cr spent against a ₹22.78 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~64.4% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 16 homes filed with MahaRERA, 6 are sold/booked (5 with registered agreements + 1 booked) and 10 remain available (~38% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹29.08 Cr in agreement value so far. Of that, ₹20.29 Cr (~70%) is already collected, ₹9.19 Cr receivable — a read on how far along these sales really are. Note: the project registers 48 homes in total, but this sold/unsold inventory filing covers only 16 of them — the other 32 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 6 registered agreements, the effective carpet rate is ₹43,850/sqft (typical range ₹26,215–₹91,641) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 2203442 sqft (41.08 sqm)₹1.58 Cr
Floor 3302991 sqft (92.03 sqm)₹3.54 Cr
Floor 44011,093 sqft (101.5 sqm)₹3.92 Cr
Floor 88014,557 sqft (423.35 sqm)₹9.92 Cr
Floor 8803684 sqft (63.56 sqm)₹2.44 Cr
Floor 8803684 sqft (63.56 sqm)₹2.44 Cr
Floor 99011,690 sqft (157.01 sqm)₹5.87 Cr
Floor 9903684 sqft (63.56 sqm)₹4.12 Cr
Floor 9903684 sqft (63.56 sqm)₹2.44 Cr
Floor 9903229 sqft (21.26 sqm)₹85.83 Lakh

⚠ The inventory filing also declares: 32 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9 and 48 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A-Wing1G+923-
B-Wing1G+925-

Unit mix on the filing: 48 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Santacruz West, Tagore Road, Borivali, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by Shalaka Nita Apt Crystal on Juhu Road, to the south by Sambhu Sadan on Tagore Road, to the east by Saturn Building And Abutting in Tagore Road and to the west by Santacruz Police Stn Corner of Juhu Rd and Linking. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Unique Shanti Developers LLP is the promoter on 10 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Unique Shanti Developers LLP project & its RERA track record →

Other flagged projects by Unique Shanti Developers LLP

Unique Shanti Developers LLP
FlaggedThane
Unique Shanti Developers LLP
FlaggedThane
Unique Shanti Developers LLP
FlaggedMumbai Suburban
Unique Shanti Developers LLP
FlaggedThane
Unique Shanti Developers LLP
Past its declared completion datePalghar
Unique Shanti Developers LLP
FlaggedThane

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Unique Elita
declared completion Dec 2019 · Ankur Shubham Developers
Unique Enclave Residency
possession by Sep 2026 · Fazal Shaikh
Unique Fortune
possession by Oct 2028 · Fazal Mehmood Shaikh
Unique Grooves
possession by Sep 2027 · Fazal Mehmood Shaikh
Unique Platinum
possession by Nov 2027 · Fazal Mehmood Shaikh
Unique Pride
declared completion Dec 2025 · Fazal Shaikh

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026