MahaRERA Property Intelligence · Mumbai Suburban

VILLA FELSTEAD

PR1180002502805 · promoter Weisshorn Realty Private

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationPR1180002502805
Registered on16 Mar 2026
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Construction Progress

MahaRERA's cost filing puts construction at ~89.3% of the estimated project cost incurred as of the last certificate (₹35.65 Cr spent against a ₹39.91 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Villa Felstead1G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Main Avenue & Sarojini Road, CTSO Bandra, Mumbai Suburban, 400054. Per the filed land record, the plot is bounded to the north by (CTS No. 426) Swati CHSL (G + 6th upper floors), to the south by The existing 18.30mt. Main Avenue Road at South side, to the east by (CTS No. 427A) Ruby Terrace (Raheja) (G + 7th upper floors) and to the west by The existing 12.20 mt. wide Sarojini Road on the West side. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district9 km
Powai / Hiranandani business park9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Vimal Apartment Chsl
declared completion Dec 2025 · Yash Realtors AND Developers
Vimala Nivas
declared completion Sep 2025 · Yash Realtors & Developers
Vinayak Heights Phase 1
declared completion Dec 2023 · Vinayak Associate
Vinayak Paradise
declared completion Mar 2018 · Avani Developers
Vinayak Residency
declared completion Sep 2023 · J.S Builders
Vinayak Shraddha Tower
declared completion Dec 2025 · K K Krishnan Construction Company PVT LT

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026