MahaRERA Property Intelligence · Pune

AARAMBH

P52100014923 · NEAR SAI MANDIR · promoter Shrivardhan Reality

Certificate SignedDue 01 May 2022

Delivery & Registration

MahaRERA registrationP52100014923
Registered on11 Jan 2018
Promoter-declared completion01 May 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
AARAMBH1G+331 May 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 May 201930 May 2020Delay in permission for revised plan from competent authority and unavailibility of construction material mainly sand in the market due to govt regulations.
31 May 201901 May 2022Due to covid 19 pandameic

Location, Land & Connectivity

Located at NEAR SAI MANDIR, 1, Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by 18 MTR ROAD, to the south by PART OF SR NO 120, to the east by VARAD VINAYAK BUILDING and to the west by 20 FT ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~121 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park121 km
Baner–Balewadi belt126 km
Pune Junction / city centre136 km
Pune Int'l Airport (Lohegaon)137 km
Kharadi / EON IT Park141 km
Magarpatta / Hadapsar IT142 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Swastik Twin Tower
possession by Jul 2026 · Swastik Builders
Asha Paradise
possession by Jul 2026 · G T Buildcon
Dhrupi Towers
possession by Jul 2026 · Not Available
RKL Durvankur Jaswand
possession by Jul 2026 · Lunkad Vishwa Developer
Amora Tower
possession by Aug 2026 · Amarnath Creativity
Prime Space
possession by Aug 2026 · Nath Estate

Major developers building in Moshi

Other RERA-registered projects in Pune

Aarambh
declared completion Jun 2019 · M/S Skyline Properties
Aarambh
declared completion Dec 2021 · Yashada Nivasa Associates
Aarambh
declared completion Jun 2023 · Shivansh Developers
Aarambh
declared completion May 2026 · R M S Developers
Aarambh
possession by Sep 2028 · Yogesh Dagdu Gaikwad
Aarambh
possession by Aug 2026 · ADI Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026