MahaRERA Property Intelligence · Pune
P52100009099 · promoter Atharva Developers Unit
| MahaRERA registration | P52100009099 |
| Registered on | 19 Aug 2017 |
| Promoter-declared completion | 30 Oct 2022 |
| Current status | Certificate Signed |
| Against today | about 45 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Atharva Developers Unit is the promoter of record on 83 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| ATHARVA VENUE | 1 | G+5 | - |
2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000269623 | 22/10/2023 | Chandrakant Vaman Kulkarni vs Swapnil Subhashchandra Sisodiya | order passed |
| CC005000000310585 | 10/03/2024 | PARESH JAYPRAKASH BHURAT vs ATHARVA DEVELOPERS UNIT 9 | order passed |
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Oct 2022 | 31 Oct 2021 | Additional FSI available due to road widening attached to our project and we applied for additional FSI with concern authority, but the same is not approved till the date of this a |
| 30 Oct 2022 | 31 Oct 2021 | Atharva Develpoer Unit 9 carring out the project “Atharva Avenue” situated at Final Plot No. 94/3/2/33 and 94/3/2/34 at Manjri Bk, Haveli, Pune 412307, registered under MahaRERA on |
Located at Haveli, Pune, 412307. Per the filed land record, the plot is bounded to the north by S NO 94, to the south by ROAD, to the east by S NO 94 and to the west by S NO 94 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~117 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 117 km |
| Baner–Balewadi belt | 123 km |
| Pune Junction / city centre | 133 km |
| Pune Int'l Airport (Lohegaon) | 134 km |
| Kharadi / EON IT Park | 137 km |
| Magarpatta / Hadapsar IT | 138 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in ATHARVA AVENUE?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026