Pune/Project record

MahaRERA · the public record

Atharva Bliss Phase II- Amenity Building

Bavdhan Budruk · M/s. Abhay Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2029declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100080179

Delivery and registration

When is the project declared for completion?

Atharva Bliss Phase II- Amenity Building is registered with MahaRERA as P52100080179 and the promoter has declared completion for 31 Mar 2029.

31 Mar 2029

declared completion

30months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100080179
Registered on05 May 2025
Promoter-declared completion31 Mar 2029
Current statusCertificate Signed
Against today30 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Atharva Bliss Phase II- Amenity Building record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Abhay Constructions is the promoter of record on 49 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

49projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Atharva Bliss Phase II- Amenity Building in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Commercial Building1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Bavdhan Budruk, S No 13/1, S No 14/1 (S No 14/1+2 Old), Pune City, Pune, 411021. Per the filed land record, the plot is bounded to the north by By Road, to the south by By S No 14 3 and 13 2, to the east by By S No 13 4 and to the west by By S No 23. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/s. Abhay Constructions is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by M/s. Abhay Constructions

M/s. Abhay Constructions
FlaggedPune

Other RERA-registered projects in Bavdhan

Purva Aspire
possession by Sep 2026 · Puravankara Limited
Marvel Selva Ridge Villa 6, 9, 11, 12
Developer in insolvency (NCLT) · possession by Dec 2026 · Marvel Omega Builders PVT LTD
Reelicon Fairy Bell
possession by Dec 2026 · Reelicon Red Homes Private Limited
Green Mint
possession by Dec 2026 · Sunil Vishwanath Salunke
Neelanchal Phase I
Not filing quarterly progress reports · possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd
Neelanchal Phase II
possession by Dec 2026 · Pinnacle Vastunirman Pvt. Ltd

Major developers building in Bavdhan

Other RERA-registered projects in Pune

Atharva Bliss Phase II- Residential Building
possession by Mar 2029 · M/s. Abhay Constructions
Atharva Feryez Residence
possession by Mar 2029 · Atharva Builders Pune Private Limited
Atharva Patson Phinix PH II
declared completion Jul 2023 · M/S Samrat Atharva Patson Builders AND D
Atharva Shrushti Wing B AND C
possession by Apr 2031 · Atharva Buildcon
Athashree
declared completion Dec 2025 · Shree Housing
Athashree
declared completion Aug 2025 · Abhivruddhi Housing LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026