Pune/Project record

MahaRERA · the public record

AUDUMBER C AND D WINGS

Hadapsar · Nirman Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100006577

Delivery and registration

When is the project declared for completion?

AUDUMBER C AND D WINGS is registered with MahaRERA as P52100006577 and the promoter has declared completion for 30 Nov 2018.

30 Nov 2018

declared completion

94months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100006577
Registered on14 Aug 2017
Promoter-declared completion30 Nov 2018
Current statusCertificate Signed
Against todayabout 94 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AUDUMBER C AND D WINGS record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AUDUMBER C AND D WINGS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
C WING1G+7-
D WING1G+7-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for AUDUMBER C AND D WINGS, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001061005/12/2017Vivek Shashikant Agarwal vs Nirman Constructionsorder passed
CC00500000001066305/12/2017Vivek Shashikant Agarwal vs Nirman Constructionsorder passed
CC00500000002289011/04/2019Anand Baburao Navale vs M/S Nirman Constructionsorder passed
CC00500000007511424/01/2021Ms Nirman Construction through its proprietor Mr Abhijeet Ramnath Gungal Abhijeet Ramnath Gunjal Gun vs Vivek Shashikant Agarwalorder passed
CC00500000007511524/01/2021Ms Nirman Construction through its proprietor Mr Abhijeet Ramnath Gungal Abhijeet Ramnath Gunjal Gun vs Vivek Shashikant Agarwalorder passed

Location, Land & Connectivity

Located at Hadapsar, Haveli, Pune, 411028. Per the filed land record, the plot is bounded to the north by S NO 82-A-36 AND 20 MTR DP ROAD, to the south by 12 MTR DP ROAD, to the east by S NO 79 AND S NO 81-6 and to the west by S NO 81 HISSA NO 9A AND 10 AND 11. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT4 km
Kharadi / EON IT Park6 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)10 km
Baner–Balewadi belt20 km
Hinjewadi Rajiv Gandhi IT Park25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing B
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Audumber Plaza
possession by Dec 2028 · Akruti Construction
Audumber Prarthi
possession by Dec 2029 · Nest Vera Buildcon
Audumber Residency
declared completion Aug 2026 · Shama Construction Through Properiter Vi
Audumber Residency
declared completion Dec 2025 · Akruti Buildcon
Audumber Residency
possession by Dec 2027 · MB Group
August Towers PH 1
possession by Dec 2028 · Bramhacorp Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026