Pune/Project record

MahaRERA · the public record

BALAJI RESIDENCY

Pune · BALAJI DEVELOPERS AND BUILDERS CO

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014385

Delivery and registration

When is the project declared for completion?

BALAJI RESIDENCY is registered with MahaRERA as P52100014385 and the promoter has declared completion for 30 Sep 2019.

30 Sep 2019

declared completion

84months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014385
Registered on29 Nov 2017
Promoter-declared completion30 Sep 2019
Current statusCertificate Signed
Against todayabout 84 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BALAJI RESIDENCY record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BALAJI RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A1G+4-
B1G+5-
C1G+5-

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for BALAJI RESIDENCY, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000005394918/01/2020Ravindra Madhukar Rupe vs Balaji developers and builders coorder passed
CC00500000005398728/01/2020Santosh pardeshi vs M/s Balaji developer and builder companyorder passed
CC00500000005412030/06/2020Kiran Bhalerao vs M/s Balaji Developers and Builders companyorder passed
CC00500000006431404/07/2020Chandrakant Bhagwan Jagtap vs M/S Balaji Developers and builders company, a registered partnership firmorder passed
CC00500000006432304/07/2020Nilesh Suresh Bhujbal vs M/s Balaji Developers and builders company a registered partnership firmorder passed

Location, Land & Connectivity

Located at Khed, Pune, 410501. Per the filed land record, the plot is bounded to the north by Remains property of Dilip Fartale, to the south by Remains property of Vishnu Fartale, to the east by Property of Dnyoba Fartale and to the west by Nighoje Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)19 km
Hinjewadi Rajiv Gandhi IT Park20 km
Baner–Balewadi belt22 km
Kharadi / EON IT Park23 km
Pune Junction / city centre24 km
Magarpatta / Hadapsar IT26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Balaji Developers AND Builders CO project & its RERA track record →

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Balaji Serenity
declared completion Dec 2024 · Balaji Buildcon
Balaji Siddhi
possession by Oct 2027 · Shri Balaji Siddhi Developers
Balaji Sudarshan
declared completion Jun 2025 · Shri Balaji Sudarshan
Balaji Vishwa
declared completion Jun 2023 · Ideal Developers
Balaji Vishwa Building D AND E
declared completion Sep 2025 · Ideal Properties
Balaji Vishwa Phase - II
declared completion Sep 2025 · JAY Balaji Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026