MahaRERA Property Intelligence · Pune

DESTINATION EL PROGRESO

P52100026761 · MOSHI PRADHIKARAN · promoter El Progreso Ventures

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP52100026761
Registered on22 Oct 2020
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, El Progreso Ventures is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
A BUILDING1G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202431 Dec 2024DUE TO COVID 19 WE HAVE NOT STARTED WORK YET.

Location, Land & Connectivity

Located at MOSHI PRADHIKARAN, BORHADEWADI , Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by GAT NO 74 P AND 75 P NEW, to the south by REMAINING LAND OF GAT NO 75 P NEW, to the east by 12 M WIDE ROAD and to the west by GAT NO 79 P NEW. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park13 km
Pune Int'l Airport (Lohegaon)13 km
Baner–Balewadi belt13 km
Pune Junction / city centre16 km
Kharadi / EON IT Park17 km
Magarpatta / Hadapsar IT19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Swastik Twin Tower
possession by Jul 2026 · Swastik Builders
Asha Paradise
possession by Jul 2026 · G T Buildcon
Dhrupi Towers
possession by Jul 2026 · Not Available
RKL Durvankur Jaswand
possession by Jul 2026 · Lunkad Vishwa Developer
Amora Tower
possession by Aug 2026 · Amarnath Creativity
Prime Space
possession by Aug 2026 · Nath Estate

Major developers building in Moshi

Other RERA-registered projects in Pune

Destination EL Progreso B Building
possession by Dec 2026 · EL Progreso Landmarks
Destination Hinjawadi
declared completion Dec 2024 · Prime SMP Developers
Destination Ishanya A Wing
declared completion Dec 2025 · Gavhane Realty
Destination Ishanya B Wing
declared completion Jun 2022 · Gavhane Realty
Destination Kshitij
declared completion May 2022 · D R Gavhane Destination
Destination Mangalam Marvel
possession by Dec 2027 · D R Gavhane Legacy

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026