EASTERN ELEGANCE

P52100013948 · MANJRI · promoter Arg Buildcon And

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100013948
Registered on02 Nov 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Arg Buildcon And is the promoter of record on 6 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
EASTERN ELEGANCE1G+1131 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MANJRI, MANJRI, Haveli, Pune, 412307. Per the filed land record, the plot is bounded to the north by SURVEY NO 93-1A-1-1A-51 AND 93-1A-1-1A-44, to the south by INTERNAL ROAD, to the east by CANAL and to the west by SURVEY NO 93-1A-2 AND 93-1B-1 2 3 4. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT3 km
Kharadi / EON IT Park5 km
Pune Junction / city centre9 km
Pune Int'l Airport (Lohegaon)9 km
Baner–Balewadi belt20 km
Hinjewadi Rajiv Gandhi IT Park25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shewalewadi

Mango Tree Villa Phase 1
possession by Jul 2026 · Palchin Real Estates Private Limited
GRM Avighna Apartment
possession by Sep 2026 · GRM Buildcon
Anand Park
possession by Dec 2026 · Shweta Vikas Bire
Godrej Sky Greens Phase 1
possession by Dec 2026 · Manjari Housing Projects LLP
Godrej Sky Greens Phase 2
possession by Dec 2026 · Manjari Housing Projects LLP
Joyville Hadapsar Annexe Phase 16
possession by Dec 2026 · Joyville Shapoorji Housing Private Limit

Major developers building in Shewalewadi

Other RERA-registered projects in Pune

Eastern Front
possession by Jun 2028 · Vishal Anjani Associates LLP
Eastern River Residency Mhada Buildings
possession by Dec 2028 · Not Available
Eastern River Residency Wing B
possession by Dec 2029 · Not Available
Eastern River Residency Wing C
possession by Dec 2028 · Not Available
Eastern River Residency Wing D
possession by Dec 2026 · Not Available
Eastern River Residency Wing F
declared completion Jun 2026 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026