Engracia B C E F

P52100007941 · Pune · promoter Pacific Orient Genesis

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP52100007941
Registered on18 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pacific Orient Genesis is the promoter of record on 24 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~75.8% of the estimated project cost incurred as of the last certificate (₹56.28 Cr spent against a ₹74.23 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 140 homes filed with MahaRERA, 140 are sold/booked (80 with registered agreements + 60 booked) and 0 remain available (~100% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹57.26 Cr in agreement value so far. Of that, ₹27.60 Cr (~48%) is already collected, ₹29.66 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 140 registered agreements, the effective carpet rate is ₹2,707/sqft (typical range ₹2,057–₹6,056) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 140 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
E BUILDING1G+742-
C BUILDING1G+1028-
F BUILDING1G+728-
B BUILDING1G+1042-

Unit mix on the filing: 140 residential.

Complaints & Orders

35 complaints are on the MahaRERA record for this project, with orders passed in 34. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000001116815/03/2018PRADEEP MOHANLAL RATHOD vs M/S PACIFIC ORIENT GENESIS ASSOCIATESorder passed
CC00500000001139317/04/2018NAGRAJ GUNDESHA vs M/s Pacific Orient Genesis Associatesorder passed
CC00500000001144217/04/2018HARESH GUNDESHA vs M/s Pacific Orient Genesis Associatesorder passed
CC00500000001158203/07/2018TAHER LIMDIWALA vs M/S PACIFIC ORIENT GENESIS ASSOCIATESorder passed
CC00500000002230825/12/2018Pradeep Rahod and Harsha Rathod vs M/s Pacific Orient Propertiesorder passed
CC00500000002241305/01/2019VILAS PARMAR vs SAMEER KHANorder passed
CC00500000002242007/01/2019DINESH GANDHI vs SAMEER KHANorder passed
CC00500000002279729/03/2019VISHAL GUPTA vs M/s. Pacific Orient Genesis Associatesorder passed
CC00500000002286509/04/2019Tina Dharne vs SAMEER SAEEDAHMED KHANorder passed
CC00500000010670403/03/2022TINA DHARNE vs PARVEZ GOUS KHAN / SABAH SAMEER KHANorder passed
CC00500000006460311/09/2020MAHADEO SOMSHANKAR KHARADE vs M/s. Pacific Orient Genesis Associatesorder passed
CC00500000006462206/10/2020TAHER SHABBIR LIMDIWALA vs M/s Pacific Orient Genesis Associetes through Mr. Sameer Khanorder passed
CC00500000007501929/12/2020Mr. Manohar Gopaldas Lulla vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007502129/12/2020Mr. Sachin Manohar Lulla vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007502229/12/2020Ashok Gopaldas Lulla vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007502315/01/2021Mr. Manohar Gopaldas Lulla vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007507815/01/2021Bharat Hasmukh Shah vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007507915/01/2021Fazila Farid Thaver vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000008529202/03/2021Mr Chetan Hasmukh Shah vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007502609/01/2021Shabbir Yousuf Lakdawala vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007502709/01/2021Abbasi Fehmida Daruwala vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007505115/01/2021RASHIDA AKBERHUSEIN HARNESSWALA vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007505215/01/2021DR SAJID GULAM MUSTAFA MOMIN vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007505315/01/2021MR AMIT DHANANJAY INAMDAR vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007505915/01/2021Nirmala Narayanji Palanji vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007506015/01/2021Niteshkumar Tarkeshwar Ojha vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007506115/01/2021Harsh Jaikishan Menghani vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007511825/01/2021Mrs Madhubala Pravin Sethia vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007511925/01/2021Mr Sharad Jadavji Chheda vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007512025/01/2021Mr Suresh Babulal Mehta vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007517605/02/2021MR HATIM FAKHRUDDIN RAMPURAWALA vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007517705/02/2021Mr Chetan Jaswant shah vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007520110/02/2021Nishrin Shabbir Banswarawala vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC00500000007520913/02/2021MRS SHALINI VISHNU WADEKAR vs m/s Pacific orient Genesis Associates through its authorised representativeorder passed
CC1250341724/09/2025Rakesh Rathi vs M/s Pacific Orient Genesis Associatespending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202429 Dec 2024Due to the death of one promoter, the project has been stalled, but now the remaining promoters are restarting it. Construction is almost complete we will require 12 months for pro
30 Dec 202331 Dec 2025The unexpected rise in raw material costs, driven by inflation and heightened demand, has created significant financial challenges for the developer. To manage this issue, the deve
30 Dec 202331 Dec 2026We would like to submit that the construction schedule of the project has been significantly impacted due to various genuine and unavoidable circumstances beyond the control of the

Location, Land & Connectivity

Located at Pune, Mohammadwadi, Pune City, Pune, 411060. Per the filed land record, the plot is bounded to the north by Survey No 37 Hissa No 1, to the south by Survey No 27, to the east by Survey No 28 and 36 and to the west by Survey No 27 and 37. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT5 km
Pune Junction / city centre7 km
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)12 km
Baner–Balewadi belt17 km
Hinjewadi Rajiv Gandhi IT Park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Undri

Lodha Pune Nibm Project
possession by Jul 2026 · Lodha Developers Limited
Samarth Rise
possession by Aug 2026 · Shri Samarth Developers
Fortune Prima
possession by Sep 2026 · Satish Shivlal Kokate
Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP

Major developers building in Undri

Other RERA-registered projects in Pune

Enigma
declared completion Jun 2018 · Emerging Landmark Realty LLP
Enjays Paramount
possession by Dec 2026 · Enjay Infra
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Enliven Homes
declared completion Jan 2021 · Siddhivinayak Properties
Ennvogue Phase I
possession by Dec 2026 · Matoshree Varad Vinayak Ventures
Envisage
possession by Sep 2029 · Arma APC Housing LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.