30 Apr 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100004357

Delivery and registration

When is the project declared for completion?

GANGA FLORENTINA PH I is registered with MahaRERA as P52100004357 and the promoter has declared completion for 30 Apr 2023.

30 Apr 2023

declared completion

41months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100004357
Registered on09 Aug 2017
Promoter-declared completion30 Apr 2023
Current statusCertificate Signed
Against todayabout 41 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GANGA FLORENTINA PH I record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GANGA FLORENTINA PH I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
C1G+1831 Dec 2020
D1G+1831 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Chief Judicial Magistrate Pune8982014Pending
Dist Court Pune2832017Disposed Off

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2023Due to covid and unavailability of resources.

Location, Land & Connectivity

Located at Bhangire Nagar, NIBM Road, Pune City, Pune, 411060. Per the filed land record, the plot is bounded to the north by 18 MTR DP ROAD, to the south by SNO 28 , to the east by S NO 36 PART and to the west by SNO 36 PART . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~137 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park137 km
Baner–Balewadi belt142 km
Pune Int'l Airport (Lohegaon)150 km
Pune Junction / city centre151 km
Kharadi / EON IT Park154 km
Magarpatta / Hadapsar IT156 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Undri

Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP
Ganga Estoria C
Not filing quarterly progress reports · possession by Dec 2026 · Meenamani Real Venture LLP
Ganga Fernhill Phase 02
possession by Dec 2026 · Meenamani Ganga Builders LLP
Sukhwani Verde
possession by Dec 2026 · Sagar Gurmukh Sukhwani

Major developers building in Undri

Other RERA-registered projects in Pune

Ganga Genesia
possession by Mar 2030 · Vardaan Lifestyle Limited
Ganga Glitz G Undri Pune
declared completion Dec 2024 · Legends County Landmark Pvt Ltd
Ganga Imperia Bldg A
possession by Mar 2030 · Ganraj Homes LLP
Ganga Imperia Commercial
possession by Dec 2029 · Ganraj Homes LLP
Ganga Ishanya AB
declared completion Dec 2019 · Mahanagar Realty
Ganga Lahari CO-Operative Housing Society LTD
possession by Oct 2026 · M/S Gokhale Constructions

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026