MahaRERA Property Intelligence · Pune

Grande Ventila Phase 1 Wing B

P52100007686 · Wagholi · promoter Satavdevelopersandbuilders

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP52100007686
Registered on17 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Grande Ventila Phase 1 Wing B1G+1231 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cjsd Pune9012011Pending

Location, Land & Connectivity

Located at Wagholi, Wagholi, Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by By Gat No 1141 Part, to the south by By Gat No 1139, to the east by By Gat No 1142P Part and to the west by By Gat No 1141 Part. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Kharadi / EON IT Park5 km
Pune Int'l Airport (Lohegaon)7 km
Magarpatta / Hadapsar IT9 km
Pune Junction / city centre13 km
Baner–Balewadi belt22 km
Hinjewadi Rajiv Gandhi IT Park26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagholi

Solvista Phase 1
possession by Sep 2026 · SSL Infrabuild LLP
Aurora 2
possession by Sep 2026 · Magnum Developers
Elite
possession by Sep 2026 · V & J Developers
Enliven Home B Wing Phase 2
possession by Sep 2026 · Siddhivinayak Properties
Godrej Greens
possession by Sep 2026 · Dream World Landmarks LLP
Kharadi Pune Phase I - Tower 1 To 4
possession by Oct 2026 · Lodha Developers Limited

Major developers building in Wagholi

Other RERA-registered projects in Pune

Grande Ventila Phase 2 Wing A
declared completion Sep 2023 · Satav Developer And Builders
Grande View 7 Capital
declared completion Dec 2024 · Chirag Developers
Grande View 7 Phase III Building K
declared completion Dec 2021 · Chirag Developers
Grande View 7 Phase IV Building F&G
declared completion Jan 2022 · Chirag Developers
Grande View 7 Phase V Building J
declared completion Jun 2023 · Chirag Developers
Grande View7 Capital 1
declared completion Dec 2025 · Chirag Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026