MahaRERA Property Intelligence · Pune

MARIGOLD

P52100005283 · SASANENAGAR · promoter Krushna Sai Buildcon

Certificate SignedDue 30 Nov 2027

Delivery & Registration

MahaRERA registrationP52100005283
Registered on11 Aug 2017
Promoter-declared completion30 Nov 2027
Current statusCertificate Signed
Against today16 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Krushna Sai Buildcon is the promoter of record on 100 projects, of which 17 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 217 homes filed with MahaRERA, 183 are sold/booked (154 with registered agreements + 29 booked) and 34 remain available (~84% sold) — selling steadily. Buyers have committed ₹55.23 Cr in agreement value so far. Of that, ₹37.89 Cr (~69%) is already collected, ₹17.34 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 183 registered agreements, the effective carpet rate is ₹5,760/sqft (typical range ₹4,089–₹10,202) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1B-101706 sqft (65.57 sqm)₹33.72 Lakh
Floor 1B-102706 sqft (65.56 sqm)₹33.72 Lakh
Floor 1B-103706 sqft (65.56 sqm)₹33.72 Lakh
Floor 1B-104706 sqft (65.57 sqm)₹33.72 Lakh
Floor 1B-105706 sqft (65.57 sqm)₹33.72 Lakh
Floor 1B-106706 sqft (65.56 sqm)₹33.72 Lakh
Floor 1B-107706 sqft (65.56 sqm)₹33.72 Lakh
Floor 1B-108706 sqft (65.56 sqm)₹33.72 Lakh
Floor 10A-1001628 sqft (58.35 sqm)₹30.01 Lakh
Floor 10A-1010454 sqft (42.21 sqm)₹21.71 Lakh
Floor 10A-1013454 sqft (42.18 sqm)₹21.69 Lakh
Floor 10A-1014454 sqft (42.17 sqm)₹21.69 Lakh
Floor 2B-201706 sqft (65.57 sqm)₹33.72 Lakh
Floor 2B-202457 sqft (42.47 sqm)₹21.84 Lakh
Floor 2B-203457 sqft (42.47 sqm)₹21.84 Lakh
Floor 2B-204457 sqft (42.46 sqm)₹21.84 Lakh
Floor 2B-205457 sqft (42.46 sqm)₹21.84 Lakh
Floor 2B-206457 sqft (42.47 sqm)₹21.84 Lakh
Floor 2B-207457 sqft (42.47 sqm)₹21.84 Lakh
Floor 2B-208631 sqft (58.65 sqm)₹30.16 Lakh
Floor 3B-301628 sqft (58.35 sqm)₹30.01 Lakh
Floor 3B-302454 sqft (42.21 sqm)₹21.71 Lakh
Floor 3B-303454 sqft (42.17 sqm)₹21.69 Lakh
Floor 3B-305454 sqft (42.18 sqm)₹21.69 Lakh
Floor 3B-306454 sqft (42.17 sqm)₹21.69 Lakh
Floor 4B-402454 sqft (42.21 sqm)₹21.71 Lakh
Floor 4B-404454 sqft (42.18 sqm)₹21.69 Lakh
Floor 4B-406454 sqft (42.17 sqm)₹21.69 Lakh
Floor 4B-407454 sqft (42.21 sqm)₹21.71 Lakh
Floor 5B-501631 sqft (58.65 sqm)₹30.16 Lakh
Floor 5B-504457 sqft (42.46 sqm)₹21.84 Lakh
Floor 7A-701631 sqft (58.65 sqm)₹30.16 Lakh
Floor 8A-816628 sqft (58.35 sqm)₹30.01 Lakh
Floor 9A-916631 sqft (58.65 sqm)₹30.16 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 217 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A Building1G+12177-
B Building1G+740-

Unit mix on the filing: 196 residential and 21 non-residential (shops/offices).

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250408719/11/2025mausam preetam batra vs Nirman Bharati Paradise Developersorder passed
CC1260429108/07/2026Bhau Jayram Pawar vs KRUSHNA SAI BUILDCON LLPpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Nov 202728 Feb 2021Due to extreme slow market conditions the sales of the project was affected and also the said project ran into delays due to slow work by Government Authorities in improving the ap
30 Nov 202728 Feb 2024Covid-19 Pandemic Declared by World Health Organization and consequent lockdown by the government further reverse migration of the labours to there native places and break in the s
30 Nov 202730 Nov 2024The project is facing delays due to a severe labour shortage, resulting in the unavailability of skilled workers. Additionally, the contractor’s performance has been adversely affe
30 Nov 202730 Nov 2027The project is facing delay due to severe labour shortage, resulting in unavailiblity of skilled worker. Additionally, the contractor performance has been adverserly affected , lea

Location, Land & Connectivity

Located at SASANENAGAR, NEAR HANDEWADI ROAD, Haveli, Pune, 411028. Per the filed land record, the plot is bounded to the north by DP ROAD S NO 54, to the south by REMAINING PART OF S NO 56, to the east by DP ROAD S NO 56 and to the west by PART OF S NO 56. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT1 km
Kharadi / EON IT Park5 km
Pune Junction / city centre6 km
Pune Int'l Airport (Lohegaon)8 km
Baner–Balewadi belt17 km
Hinjewadi Rajiv Gandhi IT Park22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing A
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Marigold
declared completion Mar 2025 · Caratlane Landmarks LLP
Marigold
possession by Dec 2028 · Sunil Radhakrishan Israni
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Marigold City
possession by Dec 2027 · Marigold Vastu LLP
Marigold Heights
possession by Dec 2029 · Vastu Developers
Marigold Residency
declared completion Jan 2025 · J W Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026