Pune/Project record

MahaRERA · the public record

Patil Hill View

Autade Handewadi · P.S.Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100045399

Delivery and registration

When is the project declared for completion?

Patil Hill View is registered with MahaRERA as P52100045399 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100045399
Registered on18 May 2022
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Patil Hill View record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Patil Hill View in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Building -11G+531 Dec 2027
Building -21G+531 Dec 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Autade Handewadi, Proposed 12 m wide road, Haveli, Pune, 411060. Per the filed land record, the plot is bounded to the north by 98-1, to the south by 98-1, to the east by 98 and to the west by 98-97. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT4 km
Kharadi / EON IT Park8 km
Pune Junction / city centre8 km
Pune Int'l Airport (Lohegaon)11 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Undri

Arnav Sokande Patil Plaza
possession by Nov 2026 · Sokande Patil Prom & Developers
Raheja Sterling - Tower 3
possession by Nov 2026 · Cavalcade Properties PVT LTD
ARV Regalia
possession by Dec 2026 · Unitree India Realty LLP
Ganga Estoria C
Not filing quarterly progress reports · possession by Dec 2026 · Meenamani Real Venture LLP
Ganga Fernhill Phase 02
possession by Dec 2026 · Meenamani Ganga Builders LLP
Sukhwani Verde
possession by Dec 2026 · Sagar Gurmukh Sukhwani

Major developers building in Undri

Other RERA-registered projects in Pune

Patil Plaza
possession by Dec 2026 · Devidas Patil
Patliputra Heights
declared completion Dec 2019 · Shankar Patloba Thakar
Pavan
possession by Sep 2027 · Not Available
Pavan Classic
declared completion Feb 2019 · Pavan Promoters
Pavan Kunj
declared completion Dec 2024 · Pavan Associates
Pavan Park
declared completion Sep 2018 · Satish Appaji Sawant

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026