MahaRERA Property Intelligence · Pune
P52100000913 · Adjucent to Bakori Village · promoter Pristine Developers
| MahaRERA registration | P52100000913 |
| Registered on | 25 Jul 2017 |
| Promoter-declared completion | 29 Feb 2020 |
| Current status | Certificate Signed |
| Against today | about 77 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Pristine Developers is the promoter of record on 13 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| B BLDG PH 1 | 1 | G+11 | 31 Aug 2019 |
| E BLDG PH 2 | 1 | G+11 | 31 Aug 2019 |
| F BLDG PH 2 | 1 | G+11 | 31 Aug 2019 |
1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000022693 | 20/02/2019 | Mrs. Pratidnya Sanjay Nashte vs M/S Pristine Developers, Through Partner-Sachin Ishwarchand Goyal | order passed |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 29 Feb 2020 | 29 Feb 2020 | Out of 3 buildings, 2 are already completed and Completion certificate & Form 4 is duly uploaded. For the last F building, application for completion was made on 08.04.2019, which |
Located at Adjucent to Bakori Village, BAKORI VILLAGE ROAD, Haveli, Pune, 412207. Per the filed land record, the plot is bounded to the north by Remaining Part of Pristine City Project, to the south by Gat 156 and 145, to the east by Gat 135 and to the west by Gat 158 and 159. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Kharadi / EON IT Park | 12 km |
| Pune Int'l Airport (Lohegaon) | 14 km |
| Magarpatta / Hadapsar IT | 15 km |
| Pune Junction / city centre | 20 km |
| Baner–Balewadi belt | 29 km |
| Hinjewadi Rajiv Gandhi IT Park | 33 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in PRISTINE CITY BEF?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Pristine Developers is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026