MahaRERA Property Intelligence · Pune

Saisparsh

P52100047216 · Kharalwadi · promoter Meghsparsh Associates

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP52100047216
Registered on12 Oct 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Meghsparsh Associates is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Building1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kharalwadi, Opp Maruti Mandir , Haveli, Pune, 411018. Per the filed land record, the plot is bounded to the north by 12 M Wide Road, to the south by CTS No 5590 5595, to the east by CTS No 5585 and to the west by CTS No 5578 5572. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimpri

Stella Apex
possession by Oct 2026 · Vastuspace Realty Promoters AND Develope
Dharampal Corporate Avenue
possession by Dec 2026 · Surender Dharampal Agarwal
Pristine Palazzo
possession by Dec 2026 · Kanha Developers
Skylish Vaastuu
possession by May 2027 · Skylish Bluediamond Innfrracon
Santoshi Mata Complex
possession by Aug 2027 · Njhb Properties
Mahindra Nestalgia
possession by Aug 2027 · Mahindra Bloomdale Developers Limited

Major developers building in Pimpri

Other RERA-registered projects in Pune

Saisurajramya Residency
declared completion May 2024 · Sai Samrajya Developers
Saivyankatesh Residency
possession by Dec 2026 · Saivyankatesh Residency
Saiyog
declared completion Jun 2018 · Kadam Developers
Saiyog Residency
declared completion Dec 2018 · Bhosale Creations
Saiyog Residency
declared completion Dec 2025 · Yogita Jitendra Rakshe
Sajan Siddhi D Wing
possession by Dec 2026 · Nemichand Bhandari Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026