Pune/Project record

MahaRERA · the public record

SATYAM NIRANJANI TOWER 1,2,3 & 4

Kalepadal · Satyam Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017871

Delivery and registration

When is the project declared for completion?

SATYAM NIRANJANI TOWER 1,2,3 & 4 is registered with MahaRERA as P52100017871 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017871
Registered on24 Sep 2018
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SATYAM NIRANJANI TOWER 1,2,3 & 4 record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Satyam Constructions is the promoter of record on 54 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

54projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SATYAM NIRANJANI TOWER 1,2,3 & 4 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Tower 11G+1131 Dec 2023
Tower 21G+1131 Dec 2023
Tower 41G+1431 Dec 2023
Tower 31G+1431 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Kalepadal, Pune - Solapur Road , Haveli, Pune, 411028. Per the filed land record, the plot is bounded to the north by portion of land out of hissa No 2, to the south by portion of land out of hissa no 4 B, to the east by Remaining portion of layout and to the west by remaining portion of layout. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Satyam Constructions is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Satyam Constructions

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing B
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Satyam Serenity - B
declared completion Jul 2025 · Vijayalaxmi Creations
Satyam Serenity - C
possession by Dec 2027 · Vijayalaxmi Creations
Satyam Shivam Phase 2
possession by Sep 2026 · Vijayalaxmi Associates
Saubhagya
declared completion May 2024 · B T Developers
Sauhrud Chsl
declared completion Jun 2023 · Kotibhaskar Infrastructures &developers
Saukhyam
possession by Apr 2027 · Ranjekar Sahasrabudhe LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026